PJM Power Providers Group v. FERC

by
The DC Circuit denied petitions for review challenging FERC's orders approving PJM's tariff that determined the rates paid to energy providers for providing electric capacity in the broad mid-Atlantic region. Petitioners argued that FERC lacked substantial evidence to approve the estimates of labor costs that formed part of the calculation of the cost of new entry; FERC should have accepted the labor-cost calculations of petitioners' expert; and FERC erred in approving another input to the estimated cost of new entry. The court held that petitioners' objections failed to undermine the substantial evidence supporting FERC's figure for the cost of new entry and failed to overcome the court's deferential standard of review. View "PJM Power Providers Group v. FERC" on Justia Law