Justia Government & Administrative Law Opinion Summaries

Articles Posted in Construction Law
by
After Rio School District’s new school was completed, the District and its general contractor (FTR) engaged in a decade-long legal battle, resulting in a judgment for FTR exceeding $9 million. Public Contract Code section 7107 allows a public entity to withhold funds due a contractor when there are liens on the property or a good faith dispute concerning whether the work was properly performed. The trial court assessed penalties against District because it did not timely release the retained funds. The court of appeal affirmed in part. A dispute over the contract price does not entitle a public entity to withhold funds due a contractor; the doctrine of unclean hands does not apply to section 7107; the trial court properly rejected the District's action under the False Claims Act, Government Code section 12650 and properly assessed prejudgment interest, subject to adjustment for any extra work claims found untimely on remand. The trial court erred in its interpretation of a contract provision imposing time limitations to submit the contractor's claims for extra work as requiring a showing of prejudice and erred in awarding fees for work not solely related to FTR's section 7107 cause of action. View "East West Bank v. Rio School Dist." on Justia Law

by
The issue this case presented for the Supreme Court's review centered on a challenge to the State Liquor Control Board's spirits distribution licensing fee structure brought by Association of Washington Spirits and Wine Distributors (Association). Specifically, the Association challenged the Board's decision to exempt distillers who distribute their own manufactured spirits and others acting as distributors pursuant to certificates of approval from contributing to a shortfall of $104.7 million in licensing fees imposed on persons holding spirits distributor licenses. The Association asked the Supreme Court to hold that the distillers must contribute proportionately to eliminating the shortfall. The Court rejected the Association's arguments, holding that the Board acted within its authority and did not act arbitrarily or capriciously. Additionally, the Board did not violate the privileges and immunities clause of article I, section 12 of the Washington State Constitution. View "Ass'n of Wash. Spirits & Wine Distribs. v. Liquor Control Bd." on Justia Law

by
The Ventura County Board planned a five-story ambulatory care clinic at the 40-acre Ventura County Medical Center. The 1993 Environmental Impact Report (EIR) stated that the building would be up to 75 feet high and included drawings that did not show building height. The Board filed a Notice of Determination (NOD) that mentioned nothing about height. Detailed plans showed the height to the roofline as 72 feet. Parapets rose to 88.5 feet. The county delayed until 2005 when Board decided to relocate the Clinic 200 feet north and 160 feet west, purportedly to reduce environmental impact and to more centrally locate the project around parking. The relocated building would be about 5 feet lower due to topography. The Board prepared an EIR "Addendum" and again filed a NOD that did not mention height. In 2007 the plans were modified to show a height of 90 feet, including parapets. In 2008, a neighbor saw an "auger rig" at the construction site and inquired. He was shocked to learn that the equipment was going to be used to construct a 90-foot high building and joined an organization that unsuccessfully sought an injunction. The court ordered preparation a supplemental EIR. Construction was completed in October 2010. The court of appeal affirmed.View "Ventura Foothill Neighbors v. Cnty. of Ventura" on Justia Law

by
Appellee, a construction company, filed a complaint for declaratory judgment against Appellants, the Arkansas State Claims Commission, the General Assembly’s Claims Review Subcommittee, the General Assembly’s Joint Budget Committee, the Arkansas State Highway Commission, and the Arkansas State Highway and Transportation Department. The circuit court granted in part and denied in part Appellants’ motion to dismiss. The Supreme Court reversed and remanded on direct appeal and granted Appellants’ motion to dismiss the cross-appeal, holding (1) Appellee’s equal-protection claim was barred by sovereign immunity; and (2) the Court lacked jurisdiction over Appellee’s cross-appeal.View "Ark. State Claims Comm'n v. Duit Constr. Co." on Justia Law

by
The Jackson County Board of Education petitioned for a writ of mandamus to direct the Circuit Court to enter an order dismissing the complaint of D.C. Pruett Contracting Company, Inc. on the ground of sovereign immunity. Pruett Contracting submitted a proposal for renovations to the Pisgah High School gymnasium. The Jackson County superintendent of education executed a purchase order authorizing Pruett Contracting to make certain renovations to the gymnasium, totaling $231,309. Pruett Contracting then began renovating the gymnasium. The Superintendent later received a letter from the State of Alabama Building Commission stating that "all work on the renovation of the Pisgah High School gymnasium [was] to stop immediately" because the project had not been submitted to or approved by the Building Commission. The Board instructed Pruett Contracting to cease all work on the gymnasium. Pruett Contracting submitted an invoice to the Board for the work that had been performed prior to the letter. Months later, because it had not received payment for its work, Pruett Contracting sued the Board, alleging breach of contract and unjust enrichment and seeking recovery of damages on theories of quantum meruit, work and labor done, open account, and account stated. The Board moved the court to dismiss the complaint, arguing that it was entitled to sovereign immunity as to the claims alleged by Pruett Contracting and that the court therefore lacked subject-matter jurisdiction over the action. Pruett Contracting responded, arguing that this case involved a protected property interest, that immunity was thus precluded, and that the court had subject-matter jurisdiction over the action. The Supreme Court concluded the Board established that it was entitled to sovereign immunity and that the trial court did not have subject-matter jurisdiction over this action; therefore, the action had to be dismissed. Because the Board demonstrated a clear legal right to an order directing the Circuit Court to dismiss Pruett Contracting's complaint, the Supreme Court granted the Board's petition for a writ of mandamus and directed the Circuit Court to dismiss Pruett Contracting's complaint. View "D.C. Pruett Contracting Company, Inc. v. Jackson County Board of Education" on Justia Law

by
The Georgia Department of Corrections (GDOC) entered into a construction contract with Lewis Walker Roofing (Walker Roofing) to re-roof several buildings at Valdosta State Prison. The Contract contained two “no assignment” clauses, and as a prerequisite to contracting with GDOC, Walker Roofing was required to obtain payment and performance bonds. It obtained such payment and performance bonds from Developers Surety and Indemnity Company. Walker Roofing did not complete its work within the time frame required by the Contract, and GDOC declared Walker Roofing in default. Developers Surety did not notify GDOC within 25 days of receipt of GDOC's notice of default regarding whether it would remedy the default or perform the contract. However, approximately three months after the declaration of default, Developers Surety gave GDOC the option of entering into a contract with another company for the completion of the work. GDOC then contracted with that company to finish the project. Under the payment and performance bonds and prior to Walker Roofing's default, Developers Surety had provided financial assistance to Walker Roofing. Developers Surety filed suit against GDOC for breach of contract and for a declaratory judgment that it had no obligation under the payment and performance bond it issued to Walker Roofing on behalf of GDOC. GDOC filed a counterclaim for breach of contract. The parties filed cross-motions for summary judgment, and the trial court determined that Developers Surety's claims were not barred by sovereign immunity and that GDOC had breached the construction contract as a matter of law. It concluded that GDOC waived its sovereign immunity by entering into the contract with Walker Roofing, and that the doctrine of equitable subrogation gave Developers Surety the ability to file suit against GDOC once it incurred liability and paid the obligations of its principal under the bond. Consequently, the trial court granted summary judgment to Developers Surety and denied it to GDOC; in the same order, the trial court entered judgment in favor of Developers Surety in the amount equal to the "financial assistance" Developers Surety provided to Walker Roofing. The Supreme Court granted certiorari to the Court of Appeals to consider whether the State’s sovereign immunity was waived for the claim Developers Surety made on its contract with the State. The Supreme Court found that immunity was indeed waived in this instance, and accordingly, it affirmed the judgment of the Court of Appeals. View "Georgia Dept. of Corrections v. Developers Surety & Indemnity Co." on Justia Law

by
The respondents, two developers and an architectural firm, Stevens & Wilkinson of South Carolina, Inc. (S&W), entered into a Memorandum of Understanding (MOU) with the City of Columbia as part of a larger project team to develop a publicly-funded hotel for the Columbia Metropolitan Convention Center. The City eventually abandoned its plan under the MOU, and the respondents brought suit on several causes of action including breach of contract and equitable relief. The City moved for summary judgment arguing the MOU was not a contract and therefore the contract claims failed. The circuit court agreed and, rejecting the equitable claims as well, granted summary judgment in favor of the City. The respondents appealed and the court of appeals affirmed in part and reversed in part. The Supreme Court reversed. Because the MOU was comprised of agreements to execute further agreements, there was no meeting of the minds on numerous material terms which had not yet been defined. Accordingly, the court of appeals was reversed with respect to that portion of the court's judgment; the Supreme Court held the MOU was unenforceable as a matter of law. The Supreme Court agreed with the circuit court and reinstated its judgment in favor of the City. View "Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia" on Justia Law

by
In April 2003, the City of Columbia entered into a Memorandum of Understanding (MOU) with Stevens & Wilkinson of South Carolina, Inc. (S&W) and several other parties, to develop a publicly-funded hotel adjacent to the Columbia Metropolitan Convention Center. As architect, S&W was to complete sufficient preliminary design work to determine a guaranteed maximum price for the project, which would be used by the City to obtain municipal bond funding to cover the cost of the hotel. Pursuant to the MOU, the construction company was to pay S&W directly. On June 26, 2003, the City received a letter stating S&W would complete its preliminary design on July 10, 2003, and would then stop working until the bond financing for the hotel was finalized. Realizing this could delay the start of construction, S&W offered to continue working the remaining ninety days until the anticipated bond closing date of October 13, 2003, but required assurance it would be compensated for the work it performed during this time frame. It provided an estimate requiring $650,000 and $75,000 per week after that. On July 30, the City approved "$650,000 for interim architectural design services for a period of 90 days prior to bond closing." The bond closing did not occur as scheduled, but S&W nevertheless continued to work. S&W submitted an invoice to the City for $697,084.79 for work that took place from July 10 to December 15, 2003. By letter dated December 17, 2003, S&W informed the construction company that the City had voted that day "to advance [$705,000.000] to the design team for design services and expenses. Because under the MOU the construction company was to pay S&W, not the City, the construction company agreed to reimburse the City for the funds paid to S&W after the bond closing. The City paid S&W's invoice. S&W continued to work on the project, but in March 2004, the City abandoned its plans under the MOU and ended its relationship with S&W. S&W received no further compensation and sued the City for breach of contract under the MOU and the July 2003 agreement. The City argued there was no separate agreement and the payment of interim fees was merely an advance on fees under the MOU and furthermore, the MOU provided that S&W was to be paid by the construction company, not the City. The trial court granted partial summary judgment in favor of S&W, finding a contract existed between it and the City. On certiorari, the City conceded a contract exists, but argued the contract terms have been satisfied. The Supreme Court found the City's arguments were unpreserved and affirmed as modified. View "Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia" on Justia Law

by
The Eastern Municipal Water District (EMWD) hired general contractor S.J. and Burkhardt, Inc. (SJB) for a public works construction project in 2006. Safeco Insurance Company (Safeco) executed performance and payment bonds for the project. Plaintiff Golden State Boring & Pipe Jacking, Inc. (GSB) was a subcontractor for the project, completing its work by September 2006, but it did not receive payment. In March 2008, SJB sent a voluntary default letter to Safeco. In July 2008, GSB sued SJB, EMWD, and Safeco for the unpaid amounts under the contract, separately seeking payment from Safeco under its payment bond. EMWD filed a cross-complaint to interplead retained sums. Safeco made a motion for summary judgment on the cause of action for payment under the bond on the ground that GSB’s claim was untimely. The trial court granted the motion, finding that there had been three cessations of labor that triggered GSB’s duty to file a stop notice in order to secure payment under Safeco's payment bond. At a subsequent court trial on the contract claims, GSB was awarded judgment against SJB, and Safeco was awarded judgment on the interpleader action. GSB appealed the summary judgment ruling, arguing: (1) the trial court erroneously overruled its objections to evidentiary matters presented in support of Safeco’s summary judgment; and (2) the court erred in finding the action was untimely. Finding no reversible error, the Court of Appeal affirmed. View "Golden State v. Eastern Municipal Water Dist." on Justia Law

by
Various Community Groups and the Detroit International Bridge Company sued the Federal Highway Administration (FHWA), challenging the Record of Decision (ROD) issued in 2009, selecting the Delray neighborhood of Detroit as the preferred location alternative for a new international bridge crossing between the U.S. and Canada. The Bridge Company owns and operates the existing Ambassador Bridge, about two miles from the proposed new crossing. The Bridge Company also owns property in the Delray neighborhood. The complaint alleged that selecting the Delray neighborhood as the preferred alternative violated the National Environmental Policy Act (NEPA); Section 4(f) of the Department of Transportation Act; Section 106 of the National Historic Preservation Act (NHPA); and “applicable legal authorities” on environmental justice, essentially because the decision was arbitrary and capricious.” The district court held that the Bridge Company had prudential standing to challenge the ROD and affirmed the ROD. The Sixth Circuit affirmed, noting extensive study of the project. View "Latin Ams. for Social & Econ. Dev. v. Adm'r of Fed. Highway Admin." on Justia Law