Justia Government & Administrative Law Opinion Summaries

Articles Posted in Energy, Oil & Gas Law
by
Continental Resources, Inc., an oil and gas production company, leases minerals from both the North Dakota Board of University and School Lands (Land Board) and the United States. The dispute centers on the entitlement to royalties from minerals extracted from the bed of Lake Sakakawea in North Dakota, which depends on the location of the Ordinary High Water Mark (OHWM). If North Dakota law and the state survey govern the OHWM, the Land Board is entitled to a larger percentage of the royalties; if the federal survey controls, the United States is entitled to a larger percentage.The United States removed the interpleader action to federal court and moved to dismiss based on sovereign immunity. The United States District Court for the District of North Dakota denied the motion, holding that under 28 U.S.C. § 2410(a)(5), the United States waived sovereign immunity because North Dakota law created a lien in favor of the United States upon Continental severing the minerals. The district court granted summary judgment in favor of the United States for lands retained since North Dakota's admission to the Union, applying federal law and the Corps Survey. It granted summary judgment in favor of the Land Board for lands reacquired by the United States, applying North Dakota law and the Wenck survey.The United States Court of Appeals for the Eighth Circuit reviewed the case. It affirmed the district court's denial of the motion to dismiss, agreeing that the United States had a lien on the disputed minerals under North Dakota law. The court also affirmed the summary judgment in favor of the Land Board, holding that North Dakota law governs the current location of the OHWM for lands reacquired by the United States. The court denied the United States' motion for judicial notice of additional documents. View "Continental Resources, Inc. v. United States" on Justia Law

by
A solar energy company, Harvey Solar I, L.L.C., applied to the Ohio Power Siting Board for a certificate to construct a solar-powered electric-generation facility in Licking County, Ohio. The project faced opposition from a local citizens group, Save Hartford Twp., L.L.C., and 11 nearby residents, who raised concerns about the environmental and economic impacts of the project, including visual impacts, flooding, wildlife disruption, noise, water quality, and glare.The Ohio Power Siting Board reviewed the application and conducted an evidentiary hearing. The board staff investigated the potential impacts and recommended approval with conditions. The board ultimately granted the certificate, subject to 39 conditions, including requirements for visual screening, floodplain coordination, wildlife impact mitigation, noise control, and stormwater management.The residents appealed the board's decision to the Supreme Court of Ohio, arguing that the board failed to properly evaluate the project's adverse impacts and that Harvey Solar did not provide sufficient information as required by the board's rules. They contended that the board's decision was unlawful and unreasonable.The Supreme Court of Ohio reviewed the case and found that the board had acted within its statutory authority and had not violated any applicable laws or regulations. The court determined that the board had sufficient evidence to make the required determinations under R.C. 4906.10(A) and that the conditions imposed on the certificate were reasonable and appropriate. The court affirmed the board's order granting the certificate for the construction, operation, and maintenance of the solar facility. View "In re Application of Harvey Solar I, L.L.C." on Justia Law

by
Enbridge Energy owns and operates a pipeline that runs from Wisconsin, through Michigan, and into Canada, crossing the Straits of Mackinac under a 1953 easement with the State of Michigan. In 2020, Michigan Governor Gretchen Whitmer informed Enbridge that the State was revoking the easement, alleging that Enbridge had violated it by creating an unreasonable risk of an oil spill. Enbridge responded by filing a federal lawsuit against Governor Whitmer and the Director of the Michigan Department of Natural Resources, seeking declaratory and injunctive relief to prevent the State from interfering with the pipeline's operation.The United States District Court for the Western District of Michigan rejected the defendants' argument that Enbridge’s claims were barred by Eleventh Amendment sovereign immunity. The court held that Enbridge’s lawsuit fell within the Ex parte Young exception to sovereign immunity, which allows federal courts to hear cases seeking prospective relief against state officials for ongoing violations of federal law.The United States Court of Appeals for the Sixth Circuit reviewed the case and affirmed the district court's decision. The Sixth Circuit held that Enbridge’s lawsuit was not barred by sovereign immunity because it sought prospective injunctive relief against state officials for alleged violations of federal law, fitting within the Ex parte Young doctrine. The court rejected the defendants' arguments that the suit was equivalent to a quiet title action or a request for specific performance of a state contract, finding that the relief sought would not divest the State of ownership or regulatory control over the land. Thus, the court concluded that Enbridge’s claims could proceed in federal court. View "Enbridge Energy, LP v. Whitmer" on Justia Law

by
Petitioners challenged an amendment to the energy facility site certificate for constructing a high-voltage electrical transmission line from Boardman, Oregon, to Hemingway, Idaho. The Energy Facility Siting Council (EFSC) had previously approved the original site certificate, which was affirmed by the court in Stop B2H Coalition v. Dept. of Energy. EFSC later approved Idaho Power’s request to amend the site certificate, expanding the site boundary and making other changes. Petitioners contested the process EFSC followed and the substance of the amendment, arguing they were entitled to a contested case proceeding and that the amendment did not comply with legal protections for watersheds and wildlife habitats.The lower court, EFSC, denied petitioners’ requests for contested case proceedings and approved the amendment. Petitioners then sought judicial review, contending that the circuit court had jurisdiction over their process challenge and that EFSC’s decisions were substantively flawed.The Supreme Court of the State of Oregon reviewed the case and held that it had jurisdiction to address the process challenge. The court found that EFSC did not err in denying the contested case proceedings, as the issues raised by petitioners were either untimely or did not present significant issues of fact or law. The court also rejected the substantive challenges, concluding that the bond requirements were adequately addressed in the original site certificate and that the expanded site boundary did not permit construction outside the micrositing corridors without further review.The Supreme Court affirmed EFSC’s final order approving the amended site certificate, holding that EFSC’s decisions were legally sound and supported by substantial evidence. View "Gilbert v. Dept. of Energy" on Justia Law

by
Sycamore Cross Solar LLC applied for certificates of public convenience and necessity (CPCN) to construct and operate a solar facility in Isle of Wight County and Surry County, Virginia. The project aimed to generate up to 240 megawatts of power and included transmission lines and associated facilities. The West Virginia & Appalachian Laborers’ District Council (WVALDC) participated in the case, arguing that the State Corporation Commission (Commission) failed to consider the benefits to specific groups as required by the Virginia Clean Economy Act (VCEA) and did not impose a local hiring condition.The Commission conducted an evidentiary hearing where Sycamore, WVALDC, and Commission staff presented their cases. Sycamore's witness testified about the project's economic benefits and commitment to local hiring, though no firm commitment was made. The Hearing Examiner recommended issuing the CPCNs without a local hiring condition but suggested notifying WVALDC about hiring timelines. The Commission adopted the Hearing Examiner's findings but declined the notification requirement, leading WVALDC to seek reconsideration.The Supreme Court of Virginia reviewed the case and affirmed the Commission's decision. The Court held that the VCEA only required the Commission to consider the benefits to specified groups, not make specific findings. The Commission's consideration of the evidence and its decision not to impose a hiring-related condition were within its discretion. The Court found no abuse of discretion, as the Commission reasonably concluded that the statutory requirements were met without the need for additional hiring conditions. View "WVALDC v. State Corporation Commission" on Justia Law

by
Hecate Energy, LLC, a developer and operator of renewable power facilities, petitioned for review of two orders by the Federal Energy Regulatory Commission (FERC). These orders approved reforms proposed by PJM Interconnection, LLC, a regional transmission grid operator, to the criteria used for processing requests to connect new electricity sources to the grid. Hecate challenged the approval of a specific aspect of these reforms: the expedited processing of interconnection requests projected to incur upgrade costs of $5 million or less. Hecate argued that this cap was arbitrary and unduly discriminatory.The Federal Energy Regulatory Commission (FERC) approved PJM's proposed reforms, including the $5 million cap, and denied Hecate's request for rehearing. FERC justified the cap by stating that projects with upgrade costs of $5 million or less were simpler and quicker to process. Hecate then petitioned the United States Court of Appeals for the District of Columbia Circuit for review, arguing that the cap was not supported by substantial evidence and that FERC failed to consider alternative eligibility rules.The United States Court of Appeals for the District of Columbia Circuit dismissed Hecate's petitions for lack of standing. The court held that Hecate's injury was not redressable because vacating FERC's approval of the $5 million cap would not likely lead to the expediting of Hecate's project. The court reasoned that PJM had multiple options to address the alleged defect without necessarily including Hecate's project in the expedited process. Therefore, Hecate failed to demonstrate that its injury would be alleviated by the court's intervention. View "Hecate Energy LLC v. FERC" on Justia Law

by
Dayton Power & Light Company, along with other utilities, sought an RTO adder from the Federal Energy Regulatory Commission (FERC) as an incentive for joining a Regional Transmission Organization (RTO). Ohio law mandates that utilities join an RTO, which led FERC to deny Dayton Power's application, arguing that the adder is meant to incentivize voluntary actions, not those required by law. The Ohio Consumers’ Counsel (OCC) challenged the existing RTO adders for other Ohio utilities, leading FERC to remove the adder for AEP but not for Duke and FirstEnergy, citing the latter's comprehensive settlement agreements.The United States Court of Appeals for the Sixth Circuit reviewed the case. The court first addressed whether the utilities could challenge the voluntariness requirement of Order 679, concluding that they could because FERC's past practices did not clearly indicate a strict voluntariness requirement. The court then interpreted Section 219(c) of the Federal Power Act, agreeing with FERC that the best reading of the statute supports the requirement that RTO membership must be voluntary to qualify for the adder.The court also considered the utilities' preemption argument, which claimed that federal law should override Ohio's mandate for RTO membership. The court held that the Federal Power Act does not preempt Ohio law, as Congress did not intend to prevent states from mandating RTO participation, especially when such mandates align with federal goals of increasing RTO membership.Finally, the court found FERC's differential treatment of AEP, Duke, and FirstEnergy to be arbitrary and capricious. It noted that all three utilities' rates included a 50-basis-point RTO adder, whether explicitly approved or impliedly included in settlements. The court affirmed FERC's denial of Dayton Power's application and the removal of AEP's adder but reversed the decision to retain the adders for Duke and FirstEnergy, remanding for further proceedings. View "Dayton Power & Light Co. v. Federal Energy Regulatory Commission" on Justia Law

by
The case involves Michigan's electricity market regulations, specifically the Individual Local Clearing Requirement (ILCR), which mandates that electricity retailers in Michigan's lower peninsula procure a certain percentage of their capacity from within that region. Plaintiffs, including Energy Michigan and the Association of Businesses Advocating Tariff Equity (ABATE), challenged the ILCR on the grounds that it violates the dormant Commerce Clause by discriminating against interstate commerce.The United States District Court for the Eastern District of Michigan initially dismissed the Michigan Public Service Commission (MPSC) on Eleventh Amendment grounds but allowed the case to proceed against individual commissioners. The court denied summary judgment motions from both sides, finding that there were factual disputes regarding whether the ILCR discriminated against interstate commerce. After a three-day bench trial, the district court concluded that the ILCR did not violate the Commerce Clause.The United States Court of Appeals for the Sixth Circuit reviewed the case and determined that the ILCR is facially discriminatory because it requires electricity to be generated within a specific geographic region, effectively favoring in-state over out-of-state electricity. The court held that this discrimination necessitates strict scrutiny, which the district court did not properly apply. The Sixth Circuit reversed the district court's judgment and remanded the case for further proceedings to determine if the ILCR can survive strict scrutiny by proving it is the only means to achieve the state's goal of ensuring a reliable energy supply. View "Energy Michigan, Inc. v. Public Service Commission" on Justia Law

by
Aclara Meters LLC owned the license for the Somersworth Hydroelectric Project on the Salmon Falls River between New Hampshire and Maine from 2016 to 2023. In 2019, Aclara sought to surrender its license to the Federal Energy Regulatory Commission (FERC). After conducting an environmental assessment, FERC authorized the surrender in 2023. American Whitewater, a conservation organization, requested a rehearing, arguing that two dams from the Project should be removed as a condition of surrender. FERC denied the request, leading Whitewater to petition the United States Court of Appeals for the District of Columbia Circuit for relief, claiming that FERC acted arbitrarily and capriciously under the Federal Power Act (FPA) and the National Environmental Policy Act (NEPA).The Commission's environmental assessment concluded that approving the surrender as proposed would not significantly affect the environment, thus an Environmental Impact Statement (EIS) was unnecessary. FERC found that removing the dams was unfeasible due to the local municipalities' reliance on the reservoir for water supply and other needs. The Commission also determined that the benefits of keeping the dams outweighed the environmental and recreational benefits of their removal. FERC's decision was based on the public interest, considering the water supply, firefighting needs, and potential impacts on local infrastructure.The United States Court of Appeals for the District of Columbia Circuit reviewed the case and denied Whitewater's petition for review. The court held that FERC's analysis was neither arbitrary nor capricious. The Commission reasonably determined that dam removal was unfeasible and appropriately assessed the public interest. The court found that FERC's decision to approve the license surrender without dam removal was supported by substantial evidence and consistent with its policies and precedents. View "American Whitewater v. FERC" on Justia Law

by
Petitioners sought review of the Federal Energy Regulatory Commission's (FERC) grant of an abandonment incentive to ITC Midwest, LLC (ITC). This incentive allows ITC to recover 100% of its prudently incurred costs if a planned transmission project is abandoned for reasons beyond its control. Petitioners, a group of organizations whose members purchase electricity, argued that ITC's ownership of the project was uncertain due to ongoing litigation challenging the Iowa Right of First Refusal statute.The Federal Energy Regulatory Commission approved ITC's request for the abandonment incentive, finding that the project met the necessary criteria, including enhancing reliability and reducing congestion. Petitioners filed a protest, which FERC rejected, stating that regulatory or litigation uncertainty does not preclude granting an abandonment incentive. Petitioners then sought rehearing, which FERC also denied, reiterating that the approval was consistent with its precedent.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court determined that petitioners lacked Article III standing because they failed to show imminent injury from FERC's orders. The court noted that petitioners' claims of potential future higher rates were speculative and not concrete or imminent. The court also found that petitioners' interest in the proper application of the law and potential collateral estoppel effects did not constitute a cognizable injury. Consequently, the court dismissed the petition for lack of jurisdiction. View "Industrial Energy Consumers of America v. FERC" on Justia Law