Justia Government & Administrative Law Opinion Summaries

Articles Posted in Energy, Oil & Gas Law
by
Summit Carbon Solutions, LLC plans to build an interstate pipeline through Iowa, passing through Shelby and Story Counties. Both counties enacted ordinances regulating pipelines, including setback, emergency response plan, and local permit requirements. Summit challenged these ordinances, claiming they were preempted by the federal Pipeline Safety Act (PSA) and Iowa law. The district court granted summary judgment in favor of Summit, permanently enjoining the ordinances.The United States District Court for the Southern District of Iowa reviewed the case and ruled in favor of Summit, finding that the PSA preempted the counties' ordinances. The court held that the ordinances imposed safety standards, which are under the exclusive regulatory authority of the federal government. The court also found that the ordinances were inconsistent with Iowa state law, which grants the Iowa Utilities Commission (IUC) the authority to regulate pipeline routes and safety standards.The United States Court of Appeals for the Eighth Circuit reviewed the case de novo and affirmed the district court's decision. The court held that the PSA preempts the Shelby and Story ordinances' setback, emergency response, and abandonment provisions. The court found that the ordinances' primary motivation was safety, which falls under the exclusive regulatory authority of the federal government. The court also held that the ordinances were inconsistent with Iowa state law, as they imposed additional requirements that could prohibit pipeline construction even if the IUC had granted a permit.The Eighth Circuit affirmed the district court's judgment in both cases, but vacated and remanded the judgment in the Story County case to the extent it addressed a repealed ordinance. View "McNair v. Johnson" on Justia Law

by
Energy Harbor, LLC, the owner and operator of the W.H. Sammis power plant, was assessed $12 million in penalties by PJM Interconnection, L.L.C. for failing to comply with PJM’s Tariff during a major winter storm in December 2022. Energy Harbor contested these penalties, arguing that the penalties were inconsistent with the terms of the Tariff, particularly the exception for maintenance outages. The Federal Energy Regulatory Commission (FERC) denied Energy Harbor’s complaint, leading Energy Harbor to petition for judicial review.The Federal Energy Regulatory Commission (FERC) reviewed Energy Harbor’s complaint and found that PJM had correctly interpreted the Tariff and calculated the penalties. FERC concluded that the maintenance outage at the Sammis Plant was not the sole cause of the performance shortfall, as the plant had sufficient capacity to meet its commitments but failed due to forced outages. Energy Harbor’s request for rehearing was denied by operation of law.The United States Court of Appeals for the District of Columbia Circuit reviewed the case and upheld FERC’s decision. The court agreed with FERC’s interpretation of the Tariff, stating that PJM correctly evaluated whether the maintenance outage was the sole cause of the performance shortfall. The court found that the Sammis Plant had enough installed capacity to meet its expected performance during the emergency, and the forced outages were also causes of the shortfall. The court also rejected Energy Harbor’s argument that the penalty exception should be assessed for each generating unit, affirming that the entire Sammis Plant was the resource at issue. Consequently, the court denied Energy Harbor’s petition for review. View "Energy Harbor, LLC v. FERC" on Justia Law

by
A regional transmission organization, Southwest Power Pool, sought to integrate the City of Nixa's transmission assets into its Zone 10 infrastructure. This integration would spread the costs of the Nixa Assets across all Zone 10 customers. Several nearby cities and utilities objected, arguing that they would bear unjustified costs without receiving corresponding benefits. They took their objections to the Federal Energy Regulatory Commission (FERC).FERC initially found insufficient evidence to determine whether the cost shift was justified and remanded the case for further proceedings. After a second hearing, an administrative law judge concluded that the integration was just and reasonable, providing incremental benefits such as improved reliability and power support for all Zone 10 customers. FERC affirmed this decision, finding that the integration's benefits justified the cost shift and denied the non-Nixa parties' request for rehearing.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court held that FERC's decision to analyze costs and benefits at the zonal level, rather than on a customer-by-customer basis, was reasonable. The court noted that requiring a hyper-granular approach would undermine the zonal system. The court also upheld FERC's consideration of unquantifiable systemwide benefits, such as improved integration and reliability, as sufficient to justify the cost shift. Finally, the court found that FERC's decision was supported by substantial evidence, including testimony and records indicating that the integration would benefit all Zone 10 customers.The court denied the petition for review, affirming FERC's decision to approve the integration and the associated cost allocation. View "Paragould Light & Water Commission v. FERC" on Justia Law

by
Equinor Energy LP operated oil and gas wells in North Dakota and contracted with its affiliate for saltwater gathering services. Versa Energy, LLC, a non-operating working interest owner in these wells, alleged that Equinor overcharged for these services. Versa petitioned the North Dakota Industrial Commission to determine the proper costs, claiming Equinor violated state law by charging more than the "reasonable actual cost" of operation.The North Dakota Industrial Commission concluded it had jurisdiction to adjudicate the dispute and determined that Equinor's costs were improper. The Commission set the proper cost for saltwater gathering services at $0.35 per barrel. Equinor appealed to the District Court of McKenzie County, which affirmed the Commission's order.The North Dakota Supreme Court reviewed the case and concluded that the Commission lacked jurisdiction to adjudicate the dispute. The court held that the Commission's regulatory authority under N.D.C.C. § 38-08-04 does not extend to adjudicating private contractual disputes. Additionally, the court determined that saltwater gathering costs are post-production costs, which fall outside the scope of "operation of a well" under N.D.C.C. § 38-08-08(2). Therefore, the Commission did not have jurisdiction under this statute to determine the proper costs for saltwater gathering.The North Dakota Supreme Court reversed the district court's order and vacated the Commission's order. View "Equinor Energy v. NDIC" on Justia Law

by
Michigan Electric Transmission Company (METC) owns a high-voltage transmission line with Michigan Public Power Agency (MPPA) and Wolverine Power Supply Cooperative. The case concerns the ownership of new transmission facilities, or "network upgrades," connecting a new solar generation park to the transmission line. METC claims exclusive ownership based on existing agreements, while MPPA and Wolverine disagree.The Federal Energy Regulatory Commission (FERC) reviewed the case and found that no agreement conclusively determined ownership rights. FERC declined to decide the ownership question, leading METC to petition for review.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court agreed with FERC's interpretation that the relevant agreements did not grant METC exclusive ownership of the network upgrades. The court found that the Styx-Murphy line qualifies as a "system" under the Transmission Owners Agreement (TOA), and since METC is not the sole owner, it cannot claim exclusive ownership. The court also found that the Styx-Murphy Agreements did not preclude MPPA and Wolverine from owning network upgrades.The court denied METC's petitions for review, upholding FERC's decision. View "Michigan Electric Transmission Company, LLC v. FERC" on Justia Law

by
The case involves Oklahoma Gas and Electric Company (OG&E) and CKenergy Electric Cooperative, Inc. (CKenergy) regarding the provision of retail electric service to two facilities located in CKenergy's certified territory. OG&E began providing service to these facilities in 2017 and 2018, respectively. CKenergy filed an application with the Oklahoma Corporation Commission (the Commission) in 2019, requesting that OG&E be enjoined from continuing to serve the facilities, arguing that OG&E was in violation of the Retail Energy Supplier Certified Territory Act (RESCTA). OG&E contended that it was allowed to serve the facilities under the one megawatt exception of RESCTA.The Commission found that the connected load for initial full operation did not meet or exceed 1,000 kW at either facility and enjoined OG&E from providing service. OG&E appealed the Commission's order. The Commission also issued an order granting OG&E's request for a stay upon posting a supersedeas bond, which CKenergy and the Oklahoma Association of Electric Cooperatives (OAEC) appealed.The Supreme Court of the State of Oklahoma reviewed the case de novo. The Court held that the term "connected load for initial full operation" in the one megawatt exception of RESCTA refers to the total nameplate values of all connected electrical equipment when full operation of the facility commences. The Court found that the Commission's interpretation ignored the plain language of the statute and was not sustained by law. It was undisputed that the connected load for each facility exceeded 1,000 kW when full operation commenced. Therefore, the one megawatt exception applied, and the Commission improperly enjoined OG&E from providing service. The Court reversed the Commission's order and deemed the appeal regarding the stay moot. View "OG&E Co. v. OKLAHOMA CORPORATION COMMISSION" on Justia Law

by
Environmental groups challenged the Bureau of Land Management’s (BLM) approval of the Willow Project, an oil and gas venture in Alaska's northern Arctic. BLM approved the project in 2023, allowing ConocoPhillips Alaska, Inc. to construct oil and gas infrastructure in the National Petroleum Reserve. BLM prepared a Supplemental Environmental Impact Statement (SEIS) after a 2021 remand by the district court, which required BLM to reassess its alternatives analysis. BLM insisted on a full field development standard to avoid piecemeal development, which led to the exclusion of certain environmentally protective alternatives.The United States District Court for the District of Alaska granted summary judgment in favor of BLM, dismissing the plaintiffs' claims under the National Environmental Policy Act (NEPA), the Alaska National Interest Lands Conservation Act (ANILCA), the Naval Petroleum Reserves Production Act (Reserves Act), and the Endangered Species Act (ESA). The district court found that BLM had rectified the errors identified in its 2021 order and that the alternatives analysis satisfied NEPA, the Reserves Act, and ANILCA. The court also held that the plaintiffs had standing but had not shown that the defendants violated the ESA.The United States Court of Appeals for the Ninth Circuit affirmed in part and reversed in part the district court’s decision. The court held that BLM did not abuse its discretion in using the full field development standard to avoid the risks of piecemeal development. However, BLM’s final approval of the project was arbitrary and capricious under the Administrative Procedure Act (APA) because it did not provide a reasoned explanation for potentially deviating from the full field development standard. The court also held that BLM’s assessment of downstream emissions complied with NEPA and that BLM did not act arbitrarily in selecting mitigation measures under the Reserves Act. The court found that BLM complied with ANILCA’s procedural requirements and that the ESA consultation was not arbitrary or capricious. The court remanded the NEPA claim without vacatur, allowing BLM to provide a reasoned explanation for its decision. View "SOVEREIGN INUPIAT FOR A LIVING ARCTIC V. UNITED STATES BUREAU OF LAND MANAGEMENT" on Justia Law

by
Kimball Wind, LLC operates a wind facility in Nebraska, generating electricity transmitted on a network owned by the Western Area Power Administration (WAPA). Before operations began, WAPA determined that a substation expansion was necessary to safely transmit the facility's electricity. WAPA offered to cover part of the expansion costs, requiring Kimball Wind to pay the rest. Kimball Wind agreed under protest, believing WAPA wrongfully made it responsible for most of the costs. Kimball Wind petitioned the Federal Energy Regulatory Commission (FERC) for an order directing WAPA to reimburse its contribution to the substation expansion.The Federal Energy Regulatory Commission determined that section 211A of the Federal Power Act does not provide for the relief sought by Kimball Wind. The Commission found that Kimball Wind did not seek an order for transmission services, which is the sole form of relief provided by section 211A. Kimball Wind then filed a request for rehearing, arguing that the order was internally inconsistent and unsupported by substantial evidence. The Commission denied the request for rehearing.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court agreed with the Commission that section 211A does not authorize the Commission to issue an order directing WAPA to reimburse Kimball Wind for its contribution to the substation expansion. The court found that Kimball Wind did not seek an order for transmission services, the only type of order the Commission may issue under section 211A. Consequently, the court denied the petition for review. View "Kimball Wind, LLC v. FERC" on Justia Law

by
The case involves the Federal Energy Regulatory Commission (FERC) extending the construction deadline for the Mountain Valley Pipeline, LLC (MVP) Southgate Project. Initially, FERC issued a certificate of public convenience and necessity for the Southgate Project in June 2020, setting a construction completion deadline of June 18, 2023. However, due to unresolved permitting issues for the Mainline, which Southgate extends from, the construction could not proceed as planned. MVP requested an extension shortly before the deadline, citing delays in Mainline permitting as the reason for not meeting the original deadline.The Commission granted MVP's extension request, finding that MVP had demonstrated good cause due to unavoidable circumstances, specifically the Mainline permitting delays. FERC also maintained that its previous assessments of market need and environmental impacts for the Southgate Project remained valid and did not require reevaluation.Eight environmental organizations petitioned for review, arguing that FERC's decision to extend the construction deadline and its refusal to revisit prior assessments were arbitrary and capricious. They contended that MVP had not made reasonable efforts to advance the Southgate Project and that the market need and environmental impact analyses were outdated.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court held that FERC reasonably found that MVP had satisfied the good cause standard for the extension, given the permitting and litigation delays with the Mainline. The court also upheld FERC's decision not to revisit its prior findings on market need and environmental impacts, concluding that the information presented by the petitioners did not constitute significant changes in circumstances. Consequently, the court denied the petitions for review. View "Appalachian Voices v. Federal Energy Regulatory Commission" on Justia Law

by
Continental Resources, Inc., an oil and gas production company, leases minerals from both the North Dakota Board of University and School Lands (Land Board) and the United States. The dispute centers on the entitlement to royalties from minerals extracted from the bed of Lake Sakakawea in North Dakota, which depends on the location of the Ordinary High Water Mark (OHWM). If North Dakota law and the state survey govern the OHWM, the Land Board is entitled to a larger percentage of the royalties; if the federal survey controls, the United States is entitled to a larger percentage.The United States removed the interpleader action to federal court and moved to dismiss based on sovereign immunity. The United States District Court for the District of North Dakota denied the motion, holding that under 28 U.S.C. § 2410(a)(5), the United States waived sovereign immunity because North Dakota law created a lien in favor of the United States upon Continental severing the minerals. The district court granted summary judgment in favor of the United States for lands retained since North Dakota's admission to the Union, applying federal law and the Corps Survey. It granted summary judgment in favor of the Land Board for lands reacquired by the United States, applying North Dakota law and the Wenck survey.The United States Court of Appeals for the Eighth Circuit reviewed the case. It affirmed the district court's denial of the motion to dismiss, agreeing that the United States had a lien on the disputed minerals under North Dakota law. The court also affirmed the summary judgment in favor of the Land Board, holding that North Dakota law governs the current location of the OHWM for lands reacquired by the United States. The court denied the United States' motion for judicial notice of additional documents. View "Continental Resources, Inc. v. United States" on Justia Law