Justia Government & Administrative Law Opinion Summaries

Articles Posted in Energy, Oil & Gas Law
by
An oil producer challenged an Alaska Department of Revenue advisory bulletin interpreting the oil tax code, arguing that the bulletin violated the Alaska Administrative Procedure Act (APA) and seeking a declaratory judgment that the interpretation was contrary to law. The Alaska Supreme Court determined the advisory bulletin could not be challenged under the APA because it was not a regulation, and that a declaratory judgment was not available because the tax dispute between the parties was not ripe. View "Exxon Mobil Corporation v. Alaska, Department of Revenue" on Justia Law

by
The Union of Concerned Scientists sought review of a Department of Energy (DOE) rule concerning the designation of “critical electric infrastructure information,” 16 U.S.C. 824o-1(a)(3), exempted from FOIA disclosure and not to be “made available by any Federal, State, political subdivision or tribal authority pursuant to any Federal, State, political subdivision or tribal law requiring public disclosure of information or records.”The Union, a national nonprofit organization consisting of scientists, engineers, analysts, and policy and communication experts who conduct “independent analyses,” argued that the rule exceeds the Department’s authority under section 215A of the Federal Power Act, is arbitrary and capricious, and was promulgated in violation of the notice and comment requirements of the Administrative Procedure Act. The D.C. Circuit dismissed the petition for lack of Article III standing. There is no indication that DOE’s rule would deprive the Union or its members of information they would receive if DOE were to apply a 2016 Rule promulgated by the Federal Energy Regulatory Commission. View "Union of Concerned Scientists v. United States Department of Energy" on Justia Law

by
In January 2020, the Energy Facility Siting Council adopted permanent rules addressing the process for amending site certificates and other procedural aspects of the council’s work. Petitioners challenged three of the council’s new rules on two grounds, contending the rules exceeded the council’s statutory authority. According to petitioners, two of the rules improperly limited party participation in contested case proceedings, and the third rule improperly authorized the expansion of site certificate boundaries without a site certificate amendment. The council disputed those arguments. The Oregon Supreme Court concurred with petitioners’ arguments and declared the three rules at issue invalid. View "Friends of Columbia Gorge v. Energy Fac. Siting Coun." on Justia Law

by
Allco Renewable Energy Limited and PLH, LLC (collectively, Allco), challenged the Vermont Public Utility Commission’s (PUC) decision establishing the avoided-cost price caps and parameters of the 2020 standard-offer program. Specifically, Allco argued the PUC failed to make a required annual determination that its pricing mechanism complied with federal law, and that its 2020 standard-offer request for proposal (RFP) was invalid because the market-based pricing mechanism used in the standard-offer program violates federal law. On the PUC's record, the Vermont Supreme Court could not conclude the agency exceeded its discretion in arriving at its determinations regarding the 2020 standard-offer program. Accordingly, the Supreme Court affirmed. View "In re Investigation to Review the Avoided Costs that Serve as Prices for the Standard-Offer Program in 2020 (Allco Renewable Energy Limited & PLH LLC, Appellants)" on Justia Law

by
Developer Chelsea Solar LLC sought a certificate of public good (CPG) to construct and operate a 2.0-megawatt (MW) solar electric generation facility off of Willow Road in Bennington, Vermont. The Public Utility Commission (PUC) denied developer’s petition, concluding that the Willow Road Facility and an adjoining facility proposed by developer, “Apple Hill Solar,” were a single 4.0-MW “plant” under the applicable definition of this term. In its decision, the PUC also considered and rejected arguments by intervenors Apple Hill Homeowners Association (AHHA) and Mt. Anthony Country Club (MACC) regarding various CPG factors. It concluded, among other things, that the project would not unduly interfere with the orderly development of the region under 30 V.S.A. section 248(b)(1) or have an undue adverse effect on aesthetics under section 248(b)(5). Developer appealed, challenging the PUC’s single-plant determination and its orders granting permissive intervention to AHHA and MACC. Intervenors cross-appealed, arguing the PUC erred in concluding the CPG factors were satisfied. The Vermont Supreme Court affirmed the PUC’s decision to deny the CPG based on its conclusion that the Willow Road and Apple Hill Facilities were a single plant. Given this conclusion, the Court did not reach the PUC’s evaluation of the CPG factors. The Court found no error in the PUC’s permissive-intervention decision. View "In re Petition of Chelsea Solar LLC" on Justia Law

by
The Supreme Court affirmed the judgment of the court of appeals reversing the decision of the trial court concluding that indemnity claims fell within an exception to an arbitration clause and that the non-signatory assignees were bound by the agreement under a theory of assumption, holding that Plaintiffs' request for a declaratory judgment was subject to mandatory arbitration.As president of Wagner Oil Company, Bryan Wagner signed a purchase and sale agreement (PSA) purchasing several assets from Apache Corporation. The PSA contained an indemnification provision and an arbitration clause. Later, third-party surface landowners filed lawsuits against Apache, seeking damages for alleged environmental contamination caused by Apache's operation of the assets before they were sold. Apache filed a demand for arbitration against Plaintiffs, including Wagner Oil and Wagner, for indemnity and defense. Plaintiffs then filed a declaratory judgment action seeking a declaration that Plaintiffs were not parties to the PSA and therefore not subject to the arbitration and indemnity clauses. The trial court denied Apache's motion to compel arbitration. The court of appeals reversed. The Supreme Court affirmed, holding (1) the indemnity disputes over third party-claims fall within the scope of the arbitration clause and outside its exception; and (2) the Wagner Oil signees were bound by the arbitration clause. View "Wagner v. Apache Corp." on Justia Law

by
The Federal Mine Safety and Health Amendments Act, 30 U.S.C. 801, requires the Secretary of the Department of Labor, through the Mine Safety and Health Administration (MSHA), to negotiate mine-specific ventilation plans with companies that operate the mines. In 2006-2018, Knight Hawk Coal operated its Prairie Eagle Mine pursuant to an MSHA-approved ventilation plan that permitted perimeter mining with 40-foot perimeter cuts. In 2018, MSHA conducted a ventilation survey at Prairie Eagle and concluded that the approved plan did not adequately ventilate the perimeter cuts. MSHA relied primarily on the results of chemical smoke tests, which involved survey team members observing smoke movement from a 44-foot distance. Months later, MSHA revoked the Prairie Eagle ventilation plan. After receiving a technical citation from MSHA for operating without an approved plan, Knight Hawk sought review by the Federal Mine Safety and Health Review Commission.The Commission’s ALJ found the revocation arbitrary and capricious, in part because the chemical smoke test results were unreliable and inconsistent and the Secretary ignored disagreements among MSHA ventilation survey team members regarding the results. The ALJ reinstated the previously-approved ventilation plan. The Commission affirmed, concluding that the Secretary failed to explain adequately why the existing ventilation plan was deficient. The D.C. Circuit denied the Secretary’s petition for review, finding that substantial evidence supports the ALJ’s finding. View "Secretary of Labor v. Knight Hawk Coal, LLC" on Justia Law

by
In 2012, U.S. Fish and Wildlife Service scientists discovered that endangered mussels were dying on the banks of Indiana's Tippecanoe River. The Service focused on the upstream Oakdale Dam, which significantly restricts the flow of water downstream in order to generate hydroelectricity and to create a lake. The Service worked with Oakdale's operator to develop new procedures that would require the dam to release more water during droughts. After a lengthy process of interagency cooperation and public dialogue, the new procedures were approved by the Federal Energy Regulatory Commission, which has licensing authority over hydroelectric dams on federally regulated waters.Local governmental entities sought review of the Commission’s decision and the Service’s Biological Opinion upon which the Commission relied. The D.C. Circuit affirmed in part. The court rejected some challenges to the validity of the Biological Opinion, which were not raised on rehearing before the Commission. There was otherwise no error in the agencies’ expert scientific analyses. The agencies failed to adequately explain why the new dam procedures do not violate a regulation prohibiting the Service from requiring more than “minor” changes to the Commission’s proposal for dam operations. Because vacating the agencies’ decisions would subject the dam operator to contradictory legal obligations imposed by separate agencies, the court remanded to the Commission without vacatur for further proceedings. View "Shafer & Freeman Lakes Environmental Conservation Corp. v. Federal Energy Regulatory Commission" on Justia Law

by
In an appeal by allowance, the Pennsylvania Supreme Court considered whether the Commonwealth, by the Office of Attorney General (OAG), could bring claims under the Pennsylvania Unfair Trade Practices and Consumer Protection Law (UTPCPL) on behalf of private landowners against a natural gas exploration and production company for its alleged deceptive, misleading, and unfair practices in obtaining natural gas leases from the landowners. The Supreme Court concluded the OAG could not bring claims under the UTPCPL on behalf of private landowners against Anadarko Petroleum Corporation and Anadarko E&P Onshore, L.L.C. (Anadarko) for its alleged unfair and deceptive practices in acquiring natural gas leases from the landowners. Furthermore, the Court found its resolution of the first issue rendered the second issue moot. The Court affirmed the portion of the Commonwealth Court’s decision that reversed the trial court order overruling Anadarko’s preliminary objections to Count III of the OAG’s second amended complaint, and otherwise reversed the order of the Commonwealth Court. View "Com. v. Chesapeake Energy, et al (Anadarko, Aplt.)" on Justia Law

by
Taylor Energy leased and operated Gulf of Mexico oil and gas properties, on the Outer Continental Shelf, offshore Louisiana. In 2004, Hurricane Ivan destroyed those operations, causing oil leaks. The Outer Continental Shelf Lands Act, the Clean Water Act, and the Oil Pollution Act required Taylor to decommission the site and stop the leaks. Taylor and the Department of the Interior developed a plan. Interior approved Taylor’s assignments of its leases to third parties with conditions requiring financial assurances. Three agreements addressed how Taylor would fund a trust account and how Interior would disburse payments. Taylor began decommissioning work. In 2009, Taylor proposed that Taylor “make the full final deposit into the trust account,” without any offsets, and retain all insurance proceeds. Interior rejected Taylor’s proposal. Taylor continued the work. In 2011, Taylor requested reimbursement from the trust account for rig downtime costs. Interior denied the request. In 2018, the Interior Board of Land Appeals (IBLA) affirmed Interior’s 2009 and 2011 Decisions.Taylor filed suit in the Claims Court, asserting contract claims. The Federal Circuit affirmed the dismissal of the suit, rejecting “Taylor’s attempt to disguise its regulatory obligations as contractual ones,” and stating an IBLA decision must be appealed to a district court.In 2018, Taylor filed suit in a Louisiana district court, seeking review of the IBLA’s 2018 decision and filed a second complaint in the Claims Court, alleging breach of contract. On Taylor's motion, the district court transferred the case, citing the Tucker Act. The Federal Circuit reversed. The Claims Court does not have subject matter jurisdiction over this case. Taylor is challenging the IBLA Decision and must do so in district court under the APA. View "Taylor Energy Co., L.L.C. v. Department of the Interior" on Justia Law