The DC Circuit denied Duke's petition for review of the Commission's denial of Duke's complaint against PJM under the Federal Power Act (FPA), 16 U.S.C. 825e. To prepare for a bitterly cold day during the January 2014 polar vortex, Duke purchased expensive natural gas which it ended up not needing. Duke then claimed that PJM, its regional transmission organization, directed it to purchase the gas and that the governing tariff provided for indemnification. The court held that the Commission's finding that PJM never directed Duke to buy gas was supported by substantial evidence on the record. Therefore, the court had no need to address Duke's remaining argument that, had such a directive been issued, the tariff would have authorized indemnification. View "Duke Energy Corp. v. FERC" on Justia Law

by
After Old Dominion found that its operational costs during the January 2014 polar vortex outstripped the amounts it could charge for electricity under the governing tariff, it asked the Commission to waive provisions of the governing tariff retroactively so that it could recover its costs. The DC Circuit denied Old Dominion's petition for review of the Commission's denial of Old Dominion's request based on the ground that such retroactive charges would violate the filed rate doctrine and the rule against retroactive ratemaking. In this case, the court afforded the Commission's interpretation of the filed tariff and the PJM Operating Agreement substantial deference where there was no dispute that the PJM Tariff's filed rate did not allow the cost recovery that Old Dominion sought. The court also denied the motion of Independent Market Monitor to intervene, but accorded it amicus curiae status. View "Old Dominion Electric Cooperative v. FERC" on Justia Law

by
The Supreme Court vacated the decision of the circuit court affirming the decision of the South Dakota Public Utilities Commission issuing an order accepting the certification of TransCanada Keystone Pipeline LP that it continued to meet permit conditions, holding that the circuit court lacked jurisdiction to hear Appellants’ appeals.The Commission granted a permit to TransCanada to construct the Keystone XL Pipeline in South Dakota. None of the parties in that proceeding appealed the order issuing a permit. Because TransCanada was unable to commence construction within four years, it certified that it continued to meet the permit conditions, as required by S.D. Codified Laws 49-41B-27. After conducting an evidentiary hearing, the Commission accepted the certification. Appellants - the Cheyenne River Sioux Tribe, the Yankton Sioux Tribe, and Dakota Rural Action - each appealed. The circuit court affirmed. The Supreme Court consolidated the appeals, vacated the circuit court’s decision, and dismissed the appeal, holding that the circuit court lacked jurisdiction to hear the appeals. View "In re Keystone XL Pipeline" on Justia Law

by
At issue in this case are the ramifications of a utility filing more than one rate with FERC during the time in which the utility negotiates an agreement with a prospective customer. The DC Circuit denied the petition for review and upheld FERC's determination that the governing rate was the rate in effect at the time the agreement was completed. Because the court found that FERC properly considered the court's findings on remand, adequately explained its decision, and properly considered the evidence, FERC did not act arbitrarily and capriciously in interpreting the new rate. View "ESI Energy, LLC v. FERC" on Justia Law

by
The Supreme Court affirmed the decision of the Board of Oil, Gas, and Mining to impose a joint operating agreement (JOA) on J.P. Furlong Company’s relationship with the party operating a drilling unit that included Furlong’s mineral lease.Furlong complained that the Board accepted, without making any of the changes to the JOA that Furlong wanted, the JOA the operator proposed. On appeal, Furlong argued that the Board erroneously applied the law to conclude that the JOA was just and reasonable and that there was not substantial evidence to support the Board’s decision. The Supreme Court affirmed, holding that the Board correctly applied the law and rendered a decision supported by substantial evidence. View "J.P. Furlong Co. v. Board of Oil & Gas Mining" on Justia Law

by
The Fifth Circuit granted Nevada's motion to dismiss Texas' petitions for declaratory and injunctive relief in a dispute arising out of the government's struggle with nuclear waste disposal under the Nuclear Waste Policy Act of 1982. Texas sought equitable relief prohibiting the Department of Energy from conducting any other consent-based siting activity and ordering defendants to finish the Yucca licensure proceedings. The court held that the deadline in 42 U.S.C. 10139(c) was not jurisdictional, and thus proceeded to consider whether the continuing violations doctrine may apply to Texas' claims; applying either versions of the continuing violations doctrine, whether as a tolling mechanism or as an apparent shorthand for an exercise in statutory interpretation, Texas' claims were still untimely; the court lacked jurisdiction to consider the Department of Energy's 2017 consent-based siting activities because they were not sufficiently final under the statute; and thus Texas' claims did not satisfy the statutory requirements of timeliness or finality. View "Texas v. United States" on Justia Law

by
The Fifth Circuit granted Nevada's motion to dismiss Texas' petitions for declaratory and injunctive relief in a dispute arising out of the government's struggle with nuclear waste disposal under the Nuclear Waste Policy Act of 1982. Texas sought equitable relief prohibiting the Department of Energy from conducting any other consent-based siting activity and ordering defendants to finish the Yucca licensure proceedings. The court held that the deadline in 42 U.S.C. 10139(c) was not jurisdictional, and thus proceeded to consider whether the continuing violations doctrine may apply to Texas' claims; applying either versions of the continuing violations doctrine, whether as a tolling mechanism or as an apparent shorthand for an exercise in statutory interpretation, Texas' claims were still untimely; the court lacked jurisdiction to consider the Department of Energy's 2017 consent-based siting activities because they were not sufficiently final under the statute; and thus Texas' claims did not satisfy the statutory requirements of timeliness or finality. View "Texas v. United States" on Justia Law

by
The DC Circuit denied the Arkansas Commission's petition for review of a final FERC order. The FERC order held that an operating company withdrawing from a multi-state energy system must continue to share the proceeds of a pre-departure settlement with the other member companies. The court held that FERC had a lawful basis to order the sharing of the benefits of the settlement and was reasoned in its allocation methodology. Therefore, FERC's order for Entergy Arkansas to share the Union Pacific Settlement benefits and its method for allocating the settlement was not arbitrary, capricious, or contrary to law. View "Arkansas Public Service Comm. v. FERC" on Justia Law

by
The DC Circuit denied the Arkansas Commission's petition for review of a final FERC order. The FERC order held that an operating company withdrawing from a multi-state energy system must continue to share the proceeds of a pre-departure settlement with the other member companies. The court held that FERC had a lawful basis to order the sharing of the benefits of the settlement and was reasoned in its allocation methodology. Therefore, FERC's order for Entergy Arkansas to share the Union Pacific Settlement benefits and its method for allocating the settlement was not arbitrary, capricious, or contrary to law. View "Arkansas Public Service Comm. v. FERC" on Justia Law

by
Appellee, the Marcellus Shale Coalition (“MSC”), filed in the Commonwealth Court’s original jurisdiction a petition for review in the nature of a complaint seeking declaratory and injunctive relief (the “Petition”), on behalf of itself and its members. MSC challenged the validity of several regulations relating to unconventional gas well operations as governed by Pennsylvania’s Oil and Gas Act of 2012 (known as Act 13). MSC alleged that certain provisions were void and unenforceable for multiple reasons, including that they were vague, lacked statutory authorization, and conflicted with other regulations and statutes applicable to the industry. Furthermore, MSC averred that the rulemaking process did not comply with the Regulatory Review Act, and that the Pennsylvania Environmental Quality Board (the “EQB”) failed to develop criteria for the Pennsylvania Department of Environmental Protection (“DEP”) to use in conditioning a drilling permit on relevant factors. The Commonwealth Court issued a single-judge, unpublished opinion and order, granting in part and denying in part preliminary injunctive relief. The Commonwealth Court also issued an order granting in part and denying in part MSC's Application for Expedited Special Relief. The order preliminarily enjoined DEP from implementing and enforcing certain sections of the Act. After its review of the parties' arguments on appeal of the Commonwealth Court order, the Pennsylvania Supreme Court affirmed in part and reversed in part. The Supreme Court affirmed the grant of preliminary injunctive relief as to Counts I and II. As for Count IV, the Court affirmed the grant of relief as to Section 78a.59c, but reversed the grant of relief as to Section 78a.59b(b). Finally, the Court reversed the grant of preliminary injunctive relief as to Count V. View "Marcellus Shale Coalition v. Dept. Environmental Protection" on Justia Law