Public Utility Commission v. RWE Renewables Americas, LLC
The case revolves around the Public Utility Commission of Texas (PUC) and two market participants, RWE Renewables Americas, LLC and TX Hereford Wind, LLC. Following Winter Storm Uri, the Legislature amended the Public Utility Regulatory Act (PURA) to require that protocols adopted by the Electric Reliability Council of Texas (ERCOT) must be approved by the PUC before they take effect. ERCOT then adopted a revision to its protocols, which was approved by the PUC, setting the price of electricity at the regulatory maximum under Energy Emergency Alert Level 3 conditions. RWE challenged the PUC's approval order in the Third Court of Appeals, arguing that the order was both substantively and procedurally invalid.The Third Court of Appeals held that the PUC's order was both substantively invalid—because the PUC exceeded its statutory authority by setting the price of electricity—and procedurally invalid—because the PUC failed to comply with the Administrative Procedure Act’s rulemaking procedures in issuing the order.The Supreme Court of Texas reviewed the case and held that the PUC’s approval order is not a “competition rule[] adopted by the commission” subject to the judicial-review process for PUC rules. The court found that PURA envisions a separate process for ERCOT-adopted protocols, and the statutory requirement that the PUC approve those adopted protocols does not transform PUC approval orders into PUC rules eligible for direct review by a court of appeals. Therefore, the Third Court of Appeals lacked jurisdiction over this proceeding. The Supreme Court of Texas vacated the court of appeals’ judgment and dismissed the case for lack of jurisdiction. View "Public Utility Commission v. RWE Renewables Americas, LLC" on Justia Law
S.W. Pub. Serv. Co. v. N.M. Pub. Regul. Comm’n
The Supreme Court of New Mexico affirmed the decision of the New Mexico Public Regulation Commission (PRC) to deny Southwestern Public Service Company’s (SPS) application for a financial incentive under the Renewable Energy Act (REA). SPS had proposed to retire renewable energy certificates (RECs) earlier than required to exceed the Renewable Portfolio Standard (RPS), and in return, requested a rate rider that would allow it to charge customers one dollar for each REC retired over the twenty percent standard. The PRC denied the application, finding that SPS’s proposal did not meet the REA’s requirement to “produce or acquire renewable energy” to qualify for an incentive. The court agreed with the PRC’s interpretation of the REA, stating that the act of retiring RECs alone does nothing to further the statute’s objectives. The court also rejected SPS’s challenges to the PRC’s amendments to Rule 572, which governs the award of incentives under the REA. The court found that the amendments did not exceed the scope of the REA, were not arbitrary or capricious, and were not otherwise unreasonable or unlawful.
View "S.W. Pub. Serv. Co. v. N.M. Pub. Regul. Comm'n" on Justia Law
Sinclair Wyoming Refining Company LLC v. EPA
This case involves a dispute over the Environmental Protection Agency's (EPA) implementation of the Clean Air Act’s Renewable Fuel Standards Program. The program requires the petroleum industry to introduce increasing volumes of renewable fuel into the nation's transportation fuel supply each year. However, Congress overestimated the speed at which domestic production of renewable fuel could expand, leading the EPA to reduce the statutorily required renewable fuel requirements annually.The case was brought before the United States Court of Appeals for the District of Columbia Circuit by two sets of petitioners. The first set, the Biofuel Petitioners, produce cellulosic biofuels and argue that the EPA's standards are set too low. The second set, the Refiner Petitioners, are fossil fuel refiners and retailers subject to the volume requirements and contend that the standards are too high.The court held that the EPA complied with the law and reasonably exercised its discretion in setting the renewable fuel requirements for the years 2020, 2021, and 2022. The court therefore denied the petitions for review. The court found that the EPA had the statutory authority to impose a supplemental volume for 2022 to make up for volume that should have been satisfied in 2016. The court also concluded that the EPA's new formula for calculating the annual percentage standards was not arbitrary or capricious. View "Sinclair Wyoming Refining Company LLC v. EPA" on Justia Law
City of Valdez v. Regulatory Commission of Alaska
The City of Valdez in Alaska appealed two orders by the Regulatory Commission of Alaska (RCA) related to the transfer of the Trans-Alaska Pipeline System (TAPS) from BP Pipelines (Alaska) Inc. (BPPA) to Harvest Alaska, LLC. The first order (Order 6) approved confidential treatment of certain financial statements submitted by the oil company and its affiliates. The second order (Order 17) approved the transfer of a required certificate and the authority to operate the pipeline. The Superior Court dismissed Valdez’s appeals, concluding that Valdez lacked standing, failed to exhaust available administrative remedies, and the case was moot. The court also ordered Valdez to pay a portion of the attorney’s fees of the oil company and other companies involved in the proceedings.The Supreme Court of the State of Alaska reversed the dismissal of the appeal of Order 6, affirmed the dismissal of the appeal of Order 17, and vacated the award of attorney’s fees. The court found that Valdez had standing to appeal both orders, the appeals were not moot, and Valdez had exhausted administrative remedies with respect to Order 6 but not Order 17. The court remanded the case for further proceedings. View "City of Valdez v. Regulatory Commission of Alaska" on Justia Law
Phoenix Capital v. Board of Oil & Gas
Phoenix Capital Group Holdings, LLC, an oil and gas mineral rights investment firm, acquired mineral interests on two sections of real property in Richland County, Montana. The previous owner, Katherine Solis, had been approached multiple times by Kraken Oil and Gas LLC, an energy production company, to secure a lease of the mineral interests or to participate in drilling wells. Solis consistently refused to engage with Kraken. After Phoenix acquired the mineral interests, it expressed a desire to participate in the oil and gas production from the wells being drilled by Kraken. However, Kraken responded that the mineral interests had been deemed “non-consent” due to Solis’s lack of participation, and it was authorized to recover risk penalties.The Board of Oil and Gas Conservation of the State of Montana held a hearing and determined that Kraken had made unsuccessful, good faith attempts to acquire voluntary pooling in the spacing unit, and that Phoenix, as a successor in interest, was bound to Solis’s decision not to participate. The Board therefore determined that the mineral interests owned by Phoenix would be subject to forced pooling and that Kraken could recover risk penalties from Phoenix. Phoenix requested a rehearing from the Board, but that request was denied. Phoenix then filed a Complaint seeking injunctive relief from the Board decision in the Thirteenth Judicial District Court, Yellowstone County. The District Court issued an Order granting Kraken and the Board’s motions for summary judgment, and dismissing Phoenix’s Complaint.In the Supreme Court of the State of Montana, Phoenix appealed the District Court's decision. The Supreme Court affirmed the lower court's decision, holding that the Board correctly interpreted the statutory force-pooling requirements, and that its decision to force pool Phoenix’s mineral interests was reasonable. The court also held that Kraken’s letters to Solis constituted written demands that gave Solis the option to either participate or face assessment of risk penalties. The court concluded that risk penalties were imposed, not pursuant to the presumption in § 82-11-202(3), MCA (2021), but under § 82-11-202(2), MCA, which requires an owner pay risk penalties when “after written demand, [the owner] has failed or refused to pay the owner’s share of the costs of development or other operations . . . .” View "Phoenix Capital v. Board of Oil & Gas" on Justia Law
Sierra Club v. Louisiana Department of Environmental Quality
The case involves a challenge by the Sierra Club to the pre-construction permits issued by the Louisiana Department of Environmental Quality (LDEQ) to Commonwealth LNG, LLC for its planned liquefied natural gas (LNG) export facility. The Sierra Club argued that the facility’s emissions would exceed National Ambient Air Quality Standards (NAAQS) and that LDEQ failed to require Commonwealth to use the best available control technology (BACT) to limit those emissions.Before the United States Court of Appeals for the Fifth Circuit, LDEQ argued that the court lacked jurisdiction to hear the case, asserting that the claim arose under state law, not federal law. However, the court found that it had jurisdiction to review the petition because when LDEQ issued the permit, it was acting pursuant to federal law, not merely state law.On the merits, the court found that LDEQ did not act arbitrarily in its use of significant impact levels (SILs) to calculate which pollutants will have an insignificant effect on the NAAQS. The court also found that LDEQ did not act arbitrarily in its use of AP-42 emission factors to determine potential emissions from an LNG facility that has not yet been built. Furthermore, the court held that LDEQ did not violate its public trustee duty under Louisiana law, which requires LDEQ to evaluate and avoid adverse environmental impacts to the maximum extent possible.The court denied Sierra Club’s petition for review and affirmed LDEQ’s permitting decision. View "Sierra Club v. Louisiana Department of Environmental Quality" on Justia Law
SAN LUIS OBISPO MOTHERS FOR PEACE V. UNITED STATES NUCLEAR REGULATORY COMMISSION
In 2022, the California Legislature directed Pacific Gas & Electric (PG&E) to extend operations at the Diablo Canyon Nuclear Power Plant, despite PG&E's previous plans to cease operations. However, the deadline for a federal license renewal application for continued operation had already passed. PG&E requested an exemption from the U.S. Nuclear Regulatory Commission (NRC) to this deadline, which the NRC granted. The NRC found that the exemption was authorized by law, would not pose an undue risk to public health and safety, and that special circumstances were present. The NRC also concluded that the exemption met the eligibility criteria for a categorical exclusion, meaning no additional environmental review under the National Environmental Policy Act was required.Three non-profit organizations, San Luis Obispo Mothers for Peace, Friends of the Earth, and the Environmental Working Group, petitioned for review of the NRC's decision. The Ninth Circuit Court of Appeals first addressed whether it had jurisdiction to hear a direct appeal from an NRC exemption decision. The court held that it did have jurisdiction, as the substance of the exemption was ancillary or incidental to a licensing proceeding. The court also concluded that the petitioners had Article III standing to bring the case, as they alleged a non-speculative potential harm from age-related safety and environmental risks, demonstrated that Diablo Canyon would likely continue operations beyond its initial 40-year license term, and alleged members’ proximity to the facility.On the merits, the court held that the NRC’s decision to grant the exemption was not arbitrary, capricious, or contrary to law. The court also held that the NRC did not act arbitrarily or capriciously in invoking the National Environmental Policy Act categorical exclusion when issuing the exemption decision. The court concluded that the NRC was not required to provide a hearing or meet other procedural requirements before issuing the exemption decision because the exemption was not a licensing proceeding. The court denied the petition for review. View "SAN LUIS OBISPO MOTHERS FOR PEACE V. UNITED STATES NUCLEAR REGULATORY COMMISSION" on Justia Law
Melone v. Coit
The case involves a dispute over the construction of an offshore wind project aimed at reducing reliance on fossil fuels. The project, proposed by Vineyard Wind 1, LLC, was expected to provide energy sufficient to power 400,000 Massachusetts homes. However, residents of Martha's Vineyard and Nantucket opposed the project, arguing that federal agencies failed to properly assess the potential impact of the project on the endangered North Atlantic right whale.Previously, the United States District Court for the District of Massachusetts had granted summary judgment in favor of the National Marine Fisheries Service (NMFS) and Vineyard Wind, rejecting the residents' challenge to a biological opinion issued by the NMFS and relied on by the Bureau of Ocean Energy Management in permitting the construction of the wind power project.In the United States Court of Appeals for the First Circuit, the residents challenged the lower court's decision, arguing that the NMFS's determination that the incidental harassment of up to twenty right whales constituted a "small number" under the Marine Mammal Protection Act (MMPA) was arbitrary, capricious, and unlawful. They also argued that NMFS's consideration of the "specified activity" and the "specific geographic region" within which that activity would occur for purposes of issuing the Incidental Harassment Authorization (IHA) to Vineyard Wind was impermissibly narrow in scope.The Court of Appeals affirmed the lower court's decision, finding that the NMFS's determination was not arbitrary or capricious and that it had properly delineated the "specific geographic region" for the purposes of the IHA. The court also found that the residents' concerns about the broader effect of the project on the right whale population were unwarranted, as the agency had considered the impact on the entire right whale population in its "negligible impact" analysis, its biological opinion, and in its participation in the Bureau of Ocean Energy Management's Environmental Impact Statement. View "Melone v. Coit" on Justia Law
Nantucket Residents Against Turbines v. U.S. Bureau of Ocean Energy Management
A group of Nantucket residents, organized as Nantucket Residents Against Turbines, challenged the approval of the Vineyard Wind project by the U.S. Bureau of Ocean Energy Management (BOEM). The project involves the construction of a wind power facility off the coast of Massachusetts. The residents alleged that the federal agencies violated the Endangered Species Act by concluding that the project's construction would not jeopardize the critically endangered North Atlantic right whale. They also claimed that BOEM violated the National Environmental Policy Act by relying on a flawed analysis by the National Marine Fisheries Service (NMFS).The case was initially heard in the United States District Court for the District of Massachusetts, which granted summary judgment in favor of the federal agencies. The court found that NMFS and BOEM had followed the law in analyzing the right whale's current status and environmental baseline, the likely effects of the Vineyard Wind project on the right whale, and the efficacy of measures to mitigate those effects. The court also found that the agencies' analyses rationally supported their conclusion that Vineyard Wind would not likely jeopardize the continued existence of the right whale.On appeal, the United States Court of Appeals for the First Circuit affirmed the judgment of the district court. The appellate court found that the lower court had correctly interpreted the law and that the federal agencies had not violated the Endangered Species Act or the National Environmental Policy Act. The court concluded that the agencies' analyses were rational and that their conclusion that the Vineyard Wind project would not likely jeopardize the continued existence of the right whale was supported by the evidence. View "Nantucket Residents Against Turbines v. U.S. Bureau of Ocean Energy Management" on Justia Law
Umatilla County v. Dept. of Energy
The case involves a dispute over the approval of a site certificate for the construction of a wind energy facility in Umatilla County, Oregon. The Energy Facility Siting Council granted the certificate to Nolin Hills Wind, LLC, despite the proposed facility not complying with a local siting criterion requiring a two-mile setback between any turbine and a rural residence. Umatilla County sought judicial review of the council's decision, arguing that the council should have required Nolin Hills to comply with the two-mile setback rule.The case was reviewed by the Supreme Court of the State of Oregon. The court noted that the council had the authority to approve the proposed energy facility despite its failure to comply with the two-mile setback rule. The court also noted that the council had the authority to approve the proposed facility even if it did not pass through more than three land use zones and even if it did not comply with all of the county’s recommended substantive criteria.The Supreme Court of the State of Oregon affirmed the council's decision, concluding that the council was authorized to issue a site certificate for the proposed wind facility notwithstanding the failure of the proposed facility to comply with the two-mile setback rule. The court found that the council was not required to reject a proposed facility simply because it did not comply with a local criterion. The court also rejected the county's argument that the council erred in concluding that the proposed facility "does otherwise comply with the applicable statewide planning goals." View "Umatilla County v. Dept. of Energy" on Justia Law