Justia Government & Administrative Law Opinion Summaries
Articles Posted in Environmental Law
In re Petition of Swanton Wind LLC
Petitioner Swanton Wind LLC appealed three determinations by the Public Utility Commission. In September 2016, petitioner requested the Public Utility Commission to grant a certificate of public good (CPG), authorizing petitioner to build a twenty-megawatt wind-powered electric-generation facility in Swanton, Vermont. Petitioner paid a $100,000 fee as part of its CPG petition, which was required by 30 V.S.A. 248b. During the next nine months, petitioner and the other parties to the proceeding engaged in substantial activity, and participating in prehearing conferences with the Commission. In early June 2017, the parties submitted filings with proposed schedules for how the proceeding should continue. As part of those filings, the Department of Public Service argued the petition and evidence were insufficient, concerned that petitioner’s filings lacked a final system-impact study. In a June 22, 2017 order, the Commission agreed, finding that it needed a final system-impact study prior to the technical hearings in order to evaluate the petition. Petitioner moved for reconsideration, which was denied. Petitioner then requested to withdraw its petition pursuant to Vermont Rule of Civil Procedure 41(a)(1), and it requested that the Commission return the $100,000 fee it paid pursuant to 30 V.S.A. 248b. In response, several parties argued that the Commission should require petitioner to pay attorney’s fees. In a January 3, 2018 order, the Commission denied petitioner’s request to return the 248b fee, saying it lacked jurisdiction to do so. It granted voluntary dismissal without prejudice pursuant to Rule 41(a)(2), rather than Rule 41(a)(1). It did not award attorney’s fees, as the parties requested, because it found no exceptional circumstances to justify an award. No party appealed that finding. However, the Commission did order that the parties could request attorney’s fees and costs for this proceeding if petitioner chose to refile the petition in the future. Petitioner appealed. The Vermont Supreme Court determined the Commission erred in concluding it lacked jurisdiction to refund the 248b fee, and erred in concluding it could reopen findings from a final order in a previous proceeding. The Court reversed and remanded the Commission’s order regarding the 248b, and struck the Commission’s order regarding attorney’s fees. View "In re Petition of Swanton Wind LLC" on Justia Law
County of Butte v. Dept. of Water Resources
The Department of Water Resources (DWR) applied to the Federal Energy Regulatory Commission (FERC or Commission) to extend its federal license to operate Oroville Dam and its facilities as a hydroelectric dam (referred to as the Oroville Facilities Project, Project, Settlement Agreement or "SA"). The plaintiffs brought this action in the superior court to stay the license procedure on the premise the environmental effects of relicensing the dam concern the operation of the dam and that jurisdiction to review the matter lies in the state courts pursuant to the California Environmental Quality Act. They claimed that a CEQA document offered to support the DWR’s application to FERC failed to consider the impact of climate change on the operation of the dam for all the purposes served by the dam. The superior court dismissed the complaint on the ground that predicting the impact of climate change is speculative. The plaintiffs appealed. A federal license is required by the Federal Power Act for the construction and operation of a hydroelectric dam. The license is issued by FERC. With one relevant exception, the FPA occupies the field of licensing a hydroelectric dam and bars review in the state courts of matters subject to review by FERC. Plaintiffs did not seek federal review as required by 18 C.F.R part 4.34(i)(6)(vii)(2003). The Court of Appeal concluded it lacked jurisdiction to hear this case. It returned the case to the trial court with an order to dismiss. View "County of Butte v. Dept. of Water Resources" on Justia Law
N.J. Highlands Coalition v. New Jersey Department of Environmental Protection .
The under review by the New Jersey Supreme Court affirmed several actions by the State Department of Environmental Protection (DEP) with regard to property in the Borough of Oakland that is subject to the Highlands Water Protection and Planning Act (Highlands Act), N.J.S.A. 13:20-1 to -35. N.J. The Supreme Court granted certiorari review only the determination that the property owner -- Bi-County Development Corporation (Bi-County) -- qualified for the exemption allowed under the Highlands Act for the construction of affordable housing projects, N.J.S.A. 13:20-28(a)(17) (Exemption 17). The issue required interpretation of Exemption 17’s language concerning expiration of its safe harbor. The Court agreed with the Appellate Division, and the DEP, that this project could proceed under Exemption 17 because its qualification had not expired. The Supreme Court affirmed the Appellate Division substantially for the reasons expressed in the published decision of the panel, adding only that affirmance was based solely on a plain language reading of the Highlands Act that did not incorporate the definition of “final approval” contained in the separate but related Municipal Land Use Law (MLUL), N.J.S.A. 40:55D-1 to -163. View "N.J. Highlands Coalition v. New Jersey Department of Environmental Protection ." on Justia Law
Georgetown Preservation Society v. County of El Dorado
Georgetown was a "quaint unincorporated Gold Rush-era hamlet" in rural El Dorado County (the County, including defendant Board of Supervisors). Developer SimonCRE Abbie, LLC and its principals wanted to erect a Dollar General chain discount store on three vacant Main Street lots. Local residents acting through plaintiff Georgetown Preservation Society (Society) objected, claiming this would impair the look of their town. After the real parties slightly modified the project, the County adopted a mitigated negative declaration, finding there was no basis to require an environmental impact report (EIR). In response to the Society’s mandamus petition, the trial court duly applied Pocket Protectors v. City of Sacramento, 124 Cal.App.4th 903 (2004), and found the Society’s evidence supported a fair argument that the project may have a significant aesthetic effect on the environment, but rejected the Society’s claims about traffic impacts and pedestrian safety, and declined to address the Society’s claim the project was inconsistent with planning and zoning norms. Accordingly, the court issued a writ of mandate compelling the County to require an EIR. On appeal, the County and real parties, supported by the League of California Cities and the California State Association of Counties (which together filed one amicus curiae brief), contended the trial court erred in finding an EIR was needed. They principally relied on the fact that the County applied its Historic Design Guide principles and found the project met aesthetic standards. The Court of Appeal disagreed with this proposed method of bypassing CEQA and instead reinforced Pocket Protectors, holding that the Society’s evidence of aesthetic impacts was sufficient to trigger the need for an EIR. "A planning or zoning decision may be entitled to greater deference than a mitigated negative declaration, but such a determination is no more than it purports to be and is not a CEQA determination." View "Georgetown Preservation Society v. County of El Dorado" on Justia Law
Ex parte Advanced Disposal Services South, LLC, et al.
Advanced Disposal Services South, LLC; Advanced Disposal Services Alabama Holdings, LLC; Tallassee Waste Disposal Center, Inc.; Advanced Disposal Services, Inc.; and Stone's Throw Landfill, LLC (collectively, "Advanced Disposal"), petitioned the Alabama Supreme Court for a writ of mandamus to direct the Circuit Court either to join the City of Tallassee ("the City") as a necessary and indispensable party to the underlying action filed by Jerry Tarver, Sr., or, alternatively, to dismiss the action in its entirety, pursuant to Rule 19, Ala. R. Civ. P. The Supreme Court granted the petition and issued the writ, making no determination whether joinder would be feasible or whether the City was an indispensable party. Tarver filed an application for rehearing, arguing in its September 28, 2018 opinion, the Supreme Court "recast" his claims to reach the conclusion that the City was a necessary party to this action. He argued that the Court's reasoning on original submission was dependent on the notion that he sought to address the whole of the effluent the City discharges into the Tallapoosa River ("the river") when, he claimed, he sought to enjoin only the quantity of the leachate Advanced Disposal deposited into the City's stabilization pond. Tarver then argued that not only did the Court's analysis depend on a recasting of his claims, but the Court also relied on facts not before the circuit court in support of that recasting, namely, "facts as to the percentage of the effluent attributable to [Advanced Disposal's] leachate compared to the percentage of the effluent attributable to other sources." In overruling Tarver's application, the Supreme Court held Tarver's arguments misapprehended its opinion; the figures cited in note 5 of the opinion on original submission were consistent with the allegations in the complaint that the stabilization pond treats "substantial amounts" of waste from parties other than Advanced Disposal. View "Ex parte Advanced Disposal Services South, LLC, et al." on Justia Law
Cowpasture River Preservation Association v. Forest Service
The Fourth Circuit granted a petition for review of the Forest Service's Special Use Permit and Record of Decision authorizing Atlantic, the project developer, to construct the Atlantic Coast Pipeline through parts of the George Washington and Monongahela National Forests and granting a right of way across the Appalachian National Scenic Trail.The court held that the Forest Service's decisions in its 2012 Planning Rule and the 2016 Amendment to the 2012 Planning Rule violated the National Forest Management Act and the court remanded for further proceedings. The court also held that the Forest Service violated the National Environmental Policy Act, and that the Forest Service lacked statutory authority pursuant to the Mineral Leasing Act to grant a pipeline right of way across the Appalachian National Scenic Trail. The court concluded that the Forest Service abdicated its responsibility to preserve national forest resources, and noted that the Forest Service's serious environmental concerns were suddenly, and mysteriously, assuaged in time to meet a private pipeline company's deadlines. View "Cowpasture River Preservation Association v. Forest Service" on Justia Law
Orange Cove Irrigation Dist. v. Los Molinos Mutual Water Co.
By a stipulated decree issued in 1920, the Tehama County Superior Court adjudicated water rights in Mill Creek. It declared the natural flow of the water up to a total rate of 203 cfs had been appropriated by the parties appearing before it for use upon their and other persons’ lands. The decree entitled these original owners of the water rights and their successors to continue diverting from Mill Creek a total of 203 cfs of water, and it allotted them shares in the amount of water each could divert. It entitled the owners to use or dispose of their share of water in any manner, at any place, or for any purpose, or in accordance with whatever agreement the owners may make with any other person or entity. As part of the decree, the court also appointed a water master of Mill Creek to implement its order. The decree gave the water master exclusive authority to divert and apportion the water during the irrigation season according to the decree’s terms, measure the diversions, and control and superintend the diversions and the gates and ditches used to divert the water. The owner of an appropriative right to water in Mill Creek sought declaratory relief to determine whether, under the judicial decree that established the right, it could: (1) use water appropriated to it on a year around basis and not only during the irrigation season; (2) use or transfer its water outside of the creek’s watershed; and (3) make these changes in the use and location of use without obtaining prior approval of the creek’s water master or the superior court. The trial court declared the decree did not give the owner these rights. The Court of Appeal agreed with the Orange Grove Irrigation District that the trial court’s holding was incorrect: the court created a condition that did not exist in the decree, and it did so based on a misunderstanding of the extent of control the decree granted to Los Molinos Mutual Water Company and of the operation of Water Code section 1706. Accordingly, the Court reversed and remanded the trial court's judgment and remanded for further proceedings. View "Orange Cove Irrigation Dist. v. Los Molinos Mutual Water Co." on Justia Law
In re Contested Case Hearing on the Water Use Permit Application Originally Filed by Kukui, Inc.
In this water use case, the Supreme Court affirmed the decision of the State of Hawaii Commission on Water Resource Management (Commission) concluding that Appellants waived the right to proceed on the contested case, holding that the Commission’s finding that Appellants waived the right to continue the case was not clearly erroneous or wrong.More than a decade ago, the Supreme Court vacated the issuance of two water use permits and remanded the matter to the Commission. On remand, the parties claiming to be the applicant’s successors in interest submitted a letter to the Commission stating that they did not have the financial resources to continue to pursue the case. Years later, Appellants filed a new water use application. The Commission treated the application as a continuation of the remanded case and then concluded that the letter constituted a waiver of Appellants’ right to continue the original proceedings. The Supreme Court affirmed, holding that the Commission did not err in finding that Appellants expressly waived their right to proceed with the contested case by their letter. View "In re Contested Case Hearing on the Water Use Permit Application Originally Filed by Kukui, Inc." on Justia Law
Spokane County v. Dep’t of Fish & Wildlife
At issue was the geographic scope of the permitting authority delegated to the Washington Department of Fish and Wildlife over hydraulic projects. A coalition of counties challenged the Department's statutory authority to regulate the construction or performance of work to occur exclusively above the ordinary high-water line. The Washington Supreme Court held the plain language of the statute at issue looked to the "reasonably certain" (not "absolutely certain") effects of hydraulic projects on state waters in determining the scope of the Department's permitting authority, and at least some projects above the ordinary high-water line were reasonably certain to affect those waters. An examination of relevant legislative history confirmed that the legislature intended the Department's regulatory jurisdiction to include projects above the ordinary high-water line that affected state waters. View "Spokane County v. Dep't of Fish & Wildlife" on Justia Law
Weyerhaeuser Co. v. United States Fish and Wildlife Service
In 2001, the Fish and Wildlife Service listed the dusky gopher frog as an endangered species, under the Endangered Species Act of 1973, 16 U.S.C. 1533(a)(1), which required the Service to designate the frog's “critical habitat.” The Service proposed designating a site in St. Tammany Parish, Louisiana (Unit 1). The frog had once lived in Unit 1, but the land had long been used as a commercial timber plantation; no frogs had been spotted there for decades. The Service concluded that Unit 1 met the statutory definition of unoccupied critical habitat because of its rare, high-quality breeding ponds and distance from existing frog populations. The Service commissioned a report, which found that designation might bar future development, depriving the owners of up to $33.9 million, but concluded that the potential costs were not disproportionate to the conservation benefits and designated Unit 1 as critical habitat. The owners sued, contending that the closed-canopy timber plantation on Unit 1 could not be critical habitat for the frog, which lives in open-canopy forests. The district court and Fifth Circuit affirmed.The Supreme Court vacated. The decision not to exclude an area from critical habitat is subject to judicial review. An area is eligible for designation as critical habitat only if it is habitat for the species. Section 1533(a)(3)(A)(i), the sole source of authority for critical-habit designations, states that when the Secretary lists a species as endangered he must also “designate any habitat of such species which is then considered to be critical habitat.” Whether the frog could survive in Unit 1; whether habitat can include areas where the species could not currently survive; and whether the assessment of the costs and benefits of designation and resulting decision were arbitrary, capricious, or an abuse of discretion, must be addressed on remand. View "Weyerhaeuser Co. v. United States Fish and Wildlife Service" on Justia Law