The Idaho Power Company appealed an order of the Idaho Public Utilities Commission that denied approval of contracts between the utility and two wind farms on the ground that the contract rate for purchasing the power was contrary to public policy because it exceeded the utility's avoided costs. Finding no reversible error, the Supreme Court affirmed. View "Idaho Power v. Grouse Creek" on Justia Law

by
NorthWestern Energy (NWE) disconnected electric service to Plaintiff's residence based on an outstanding balance on Plaintiff's utility bill. Plaintiff filed an action alleging property damage due to NWE's negligence and negligence per se, claiming that the termination of his electric service caused his furnace to fail, which led to water pipes freezing and bursting. NWE filed a motion to dismiss based on lack of subject-matter jurisdiction for Plaintiff's failure to exhaust administrative remedies before the Public Service Commission (PSC). The district court granted NWE's motion and dismissed the action. The Supreme Court reversed, holding that the PSC had no authority to adjudicate Plaintiff's damage claim, and a negligence action seeking damages could be maintained against the power company in district court. View "Schuster v. NorthWestern Energy Co." on Justia Law

by
The Village of Bement, Piatt County, has a five-year contract, under which E.R.H. Enterprises operates and maintains the Village’s potable water facility and parts of its water delivery infrastructure. The Department of Labor issued a subpoena to E.R.H.’s attorney seeing employment records as part of an investigation under the Prevailing Wage Act, 820 ILCS 130/0.01. E.R.H. asserted that it was exempt from the Act as a public utility. The trial court ruled in favor of the Department and ordered E.R.H. to provide the requested documents, noting that the company was not regulated by the Illinois Commerce Commission. The appellate court reversed. The Illinois Supreme Court reversed the appellate court, finding that E.R.H. is simply an outside contractor. View "People v. IL Dep't of Labor" on Justia Law

by
Appellant purchased telephone and other telecommunications services from (intervening) Appellee at wholesale rates and resold the services to end-user consumers at retail rates. Appellant filed a complaint with the Public Utilities Commission (PUCO) alleging that Appellee had overcharged for its services and submitted inaccurate billing invoices to Appellant, among other things. PUCO denied the complaint, concluding that Appellant failed to submit sufficient credible evidence that Appellee had refused to issue credits for valid billing disputes. The Supreme Court affirmed, holding that Appellant failed to carry its burden on appeal of demonstrating that PUCO's orders were unreasonable or unlawful. View "OHIOTELNET.COM, INC. v. Windstream Ohio, Inc." on Justia Law

by
Appellant owned and operated two mobile home parks. In 2000, Appellant changed its practice of including in the rent it charged tenants the cost of water it purchased from the City for the tenants' use. Instead, Appellant installed water meters on each trailer lot and began charging tenants for water usage separately from their rent. In 2008, the Public Service Commission (PSC) determined that Appellant was a public utility and therefore subject to regulation by the PSC. The district court affirmed. The Supreme Court affirmed, holding (1) because Appellant metered a commodity utility to its tenants, it was a public utility under Wyoming law and therefore subject to PSC regulation; and (2) PSC's regulation of Appellant did not violate Appellant's equal protection rights. View "Gosar's Unlimited Inc. v. Wyo. Pub. Serv. Comm'n" on Justia Law

by
The issue on appeal before the Supreme Court in this case centered on the limits of the Public Utility Commission's (PUC) authority to allocate costs associated with a rail-highway crossing project. The Commonwealth Court held that the Commission could not allocate costs to a transportation utility that regularly uses a railroad-crossing site and does not own real estate or properties there. The Commission and Intervenors argued that the PUC has broad discretion not only to determine the allocation of costs to "concerned parties," but also to determine which parties are "concerned" in the first instance. Counterbalancing the Commission's and Intervenors' remarks about equities, Norfolk Southern Railway questioned why it should contribute to the remediation of deteriorating infrastructure over which it had no control. Upon review, the Supreme Court held that a transportation utility need not own facilities at a rail-highway crossing to be a concerned party for purposes of the PUC's cost-allocation jurisdiction and authority, at least where the utility conducts regular operations at the crossing and may enforce an easement-based right of way. View "Norfolk Southern Railway v. PUC" on Justia Law

by
Appellant filed a complaint and amended complaint against the Ohio Edison Company, a public utility, alleging that Ohio Edison had unlawfully removed the electric meter from his property and disconnected his electric service. The Public Utilities Commission found that Ohio Edison was justified in removing the meter and terminating electric service where (1) Appellant had never made an application for new service under Ohio Edison's tariff and therefore was not a customer of Ohio Edison, and (2) Ohio Edison properly removed the electric meter without prior notice because the meter had been tampered with and was a safety hazard. The Supreme Court affirmed, holding that Appellant failed to demonstrate that the Commission erred in finding that (1) Appellant was not a customer of Ohio Edison at the property in question; and (2) Ohio Edison had lawfully disconnected electric service to the property. View "Smith v. Ohio Edison Co." on Justia Law

by
In 2009, Minnesota Power sought an increase in service rates of approximately 18.9 percent. As part of its submission to the Minnesota Public Utilities Commission, Minnesota Power also requested an interim rate increase of approximately $73.3 million. The Commission decided to set the interim rate increase at approximately $48.5 million after finding exigent circumstances existed. The court of appeals affirmed, concluding that the Commission did not err in finding exigent circumstances and did not abuse its discretion in setting interim rates. The Supreme Court affirmed, holding that substantial evidence supported the Commission's decision to set Minnesota Power's interim rate increase at $48.5 million. View "In re Application of Minn. Power for Auth. to Increase Rates for Elec. Serv. in Minn." on Justia Law

by
Appellants, the New Mexico Attorney General and New Mexico Industrial Energy Consumers, asked the Supreme Court to vacate and annul the final order in PRC Case No. 11-00308-UT (Case 308 Final Order) because it permitted Public Service Company of New Mexico (PNM) to earn returns on the operating expenses incurred from energy efficiency programs. Appellants argue that such returns are inconsistent with New Mexico law. Upon review, the Supreme Court held that Case 308 Final Order was consistent with the PRC’s ratemaking authority under the New Mexico Public Utility Act, the New Mexico Efficient Use of Energy Act, and with the Court's holding in "Attorney General v. New Mexico Public Regulation Commission" (258 P.3d 453). Furthermore, the Court held that Case 308 Final Order was supported by substantial evidence and was neither arbitrary nor capricious. Accordingly, the Court affirmed the Case 308 Final Order. View "NMAG v. NMPRC" on Justia Law

by
Appellant, a public utility (Utility), provided natural gas to intervening Appellee, an apartment complex. In 2008, Utility informed Appellee that it would disconnect gas service to the entire complex if Appellee did not bring all apartment units into compliance with the National Fire Protection Association's National Fuel Gas Code (NFG Code) within two months. Appellee subsequently filed a complaint against Utility with the Public Utilities Commission (Commission), alleging that Utility had unreasonably and unlawfully threatened to disconnect gas service to all units if Appellee refused to retrofit the ventilation system in each apartment to meet NFG Code requirements. The complaint requested that the Commission prohibit Utility from terminating service and requiring expensive remedial construction. The Commission found in favor of Appellee. The Supreme Court affirmed, holding that none of Utility's six propositions of law had merit. View "Cameron Creek Apartments v. Columbia Gas of Ohio, Inc." on Justia Law