Conservation Northwest v. Commissioner of Public Lands
The issue this case presented for the Washington Supreme Court's review centered on the Department of Natural Resources' ("DNR") land management strategies applicable to certain federal land grants (“state lands”) and county land grants (“forest board lands”), which involves harvesting timber from these lands to generate revenue for state institutions and counties. The petitioners, a group of individuals and nonprofit organizations (collectively Conservation NW), challenged DNR’s land management strategies on the grounds they violated the mandate under Washington Constitution article XVI, section 1 that “[a]ll the public lands granted to the state are held in trust for all the people.” Conservation NW argued DNR’s strategies prioritized maximizing revenue from timber harvests and undercut its obligation to manage granted lands for the broader public interest, which would have been better served by prioritizing conservation and efforts to mitigate climate change, wildfires, and land erosion. DNR contended it had a trustee obligation to manage the state and forest board lands specifically for the state institutions enumerated in the Enabling Act and the county beneficiaries. DNR acknowledged its land management strategies generated revenue but not “at the expense of forest health.” The trial court dismissed Conservation NW’s lawsuit against DNR pursuant to County of Skamania v. Washington, 685 P.2d 576 (1984), establishing DNR as a trustee under the Enabling Act. The Supreme Court affirmed the trial court's dismissal of the case. View "Conservation Northwest v. Commissioner of Public Lands" on Justia Law
Stergiou et al. v. City of Dover
Intervenors Micheline Elias and The Fakhourys, LLC (collectively, the developer), appealed a superior court order denying their motion to dismiss a petition filed by the petitioners, George Stergiou, Jen McCarthy, Brendan Sullivan, and Kirankumar Tamminidi (the abutters), challenging a conditional site plan approval granted to the developer by the planning board (the Board) for the respondent City of Dover (the City). In January 2019, the developer applied to the Board for permission to construct a mixed use development project in Dover. After a public hearing, the Board conditionally approved the site plan (the 2019 Approval). The 2019 Approval and Chapter 153, Article II, Section 153-8 of the City’s site review regulations (the Certification Provision) required the developer to provide the Board with copies of the plan in various formats within 90 days. Due to unforeseen circumstances, the developer was unable to meet this deadline. In July 2020, the developer asked the Board to “re-approve” the 2019 application so that the project could move forward. The Board held a duly-noticed meeting, at which it conditionally re-approved the Site Review Plan subject to specified “Conditions to be Met Prior to the Signing of Plans” (the 2020 Approval). The abutters petitioned pursuant to RSA 677:15, challenging the 2020 Approval as unlawful and unreasonable. The New Hampshire Supreme Court concluded the 2019 Approval was not timely appealed and remained in force, and the 2020 Approval was void ab initio. The Court thus affirmed in part, reversed in part, and remanded with instructions to dismiss, with prejudice, the abutters’ RSA 677:15, I, appeal as untimely. View "Stergiou et al. v. City of Dover" on Justia Law
Jack Lingo Asset Management, LLC v. Board of Adjustment of the City of Rehoboth Beach
Jack Lingo Asset Management (“Lingo”) owned and occupied property at 240 Rehoboth Avenue in Rehoboth Beach, Delaware. The second story only covered a portion of the first, leaving a flat roof over the rest of the ground floor. In 2018, Lingo wanted to convert the second floor from residential to office space. As part of this project, it sought permission from the City of Rehoboth Beach (the “City”) to build an unroofed, railed walkway extending from the second floor over the flat roof to a stairway leading down to Christian Street. The exit walkway would not be visible from the main thoroughfare. The City denied Lingo’s application, finding the railings surrounding the walkway would technically expand the Gross Floor Area of 240 Rehoboth Avenue under Section 270 of the City's Zoning Code. This expansion would, in turn, require Lingo to provide an additional parking spot, which it had no room to do. Lingo appealed the denial. The Board of Adjustment of the City of Rehoboth Beach affirmed in two decisions, and the Superior Court agreed. The Delaware Supreme Court reversed, finding that the Rehoboth Zoning Code in effect at the time of Lingo’s application did not clearly and unambiguously establish that the proposed egress structure would increase the Gross Floor Area of 240 Rehoboth Avenue. Applying settled canon that zoning ambiguities be construed in the property owner's favor, the Supreme Court vacated the Board's decision. View "Jack Lingo Asset Management, LLC v. Board of Adjustment of the City of Rehoboth Beach" on Justia Law
International Investors v. Town Plan & Zoning Commission
The Supreme Court reversed the appellate court's judgment reversing in part the decision of the Town Plan and Zoning Commission of the Town of Fairfield extending its approvals of a special permit and a coastal site plan review granted to Fairfield Commons, LLC, holding that a local zoning authority may not, by regulation, condition the continuing validity of a special permit on completing development in connection with the permitted use within a period of time that is shorter than the statutory period.The appellate court in this case affirmed the trial court's judgment concluding that the Commission improperly granted Fairfield Commons' request for an extension of its special permit deadline to complete development but reversed the court's conclusion that the special permit could not be subject to a temporal limitation as a matter of law. The Supreme Court reversed, holding (1) a special permit regulation may not prescribe a shorter time limitation for completing development than the statutory period set forth for completion of development in connection with an accompanying site plan under Conn. Gen. Stat. 8-3(i) and (m); and (2) the appellate court incorrectly concluded that the special permit at issue expired in April 2011. View "International Investors v. Town Plan & Zoning Commission" on Justia Law
29 McKown LLC v. Town of Boothbay Harbor
The Supreme Judicial Court vacated the judgment of the superior court affirming the decision of the Town of Boothbay Harbor's Board of Appeals (BOA) denying 29 McKown, LLC's administrative appeal from a code enforcement officer's (CEO) decision to life a stop work order he had issued to Harbor Crossing during the construction of the building, holding that 29 McKown was deprived of administrative due process.In this case concerning a real estate office building constructed by Harbor Crossing in Boothbay Harbor, 29 McKown sought review of the denial of its McKown's appeal. The superior court affirmed the BOA's decision. The Supreme Judicial Court vacated the order below, holding (1) 29 McKown was deprived of administrative due process; and (2) the CEO did not issue a judicially-reviewable decision in lifting the stop work order. View "29 McKown LLC v. Town of Boothbay Harbor" on Justia Law
City of Gulfport v. Cowan Road & Hwy 90, LLC, et al.
In 2008, the City of Gulfport undertook a project to replace the infrastructure associated with its water and sewer systems relating to damage caused by Hurricane Katrina in 2005. The repair project involved federal, state, and local agencies and ultimately cost approximately $85 million to complete. The original design of the Area 3B project, the sewer infrastructure that crossed the Cowan Road property located north of U.S. Highway 90 and east of Highway 605 were to be replaced, and the new infrastructure was to be installed within the City’s existing easements across the properties. The Cowan Road property at issue was located in the Area 3B geographic zone. Robert “Kris” Riemann, P.E., then-director of the City’s department of public works, was notified that John Felsher had inquired about relocating the sewer infrastructure in Area 3B. Based on an agreement with Felsher to relocate the utilities, the City had the Area 3B design drawings redrafted to move the utilities. The City's project manager was notified that the discovery of underground telephone lines and other utilities required that the sewer line being relocated had to cut the northwest corner of the property. Cowan Road filed a complaint in the Chancery Court of Harrison County, Mississippi, advancing a claim for inverse condemnation against the City. The chancery court transferred the case to the Special Court of Eminent Domain in Harrison County. Due to the jurisdictional limits of county court, the case ended up in Harrison County Circuit Court. The circuit court entered an order granting the motion for partial summary judgment filed by the City on the issue of the date of the taking. The parties eventually settled the reverse condemnation claim, and the City agreed to pay $100,000 to Cowan Road & Hwy 90, LLC, for the improper and unlawful taking of its property. The issue before the Mississippi Supreme Court centered on the circuit court's grant of attorneys' fees and expenses: Gulfport argued that Cowan Road should not have been allowed to recover attorneys’ fees under Section 43-37-9. Finding that the statute applied and fees were appropriate, the Supreme Court affirmed. However, the Court found the trial judge abused his discretion by disallowing requests for postjudgment interest. View "City of Gulfport v. Cowan Road & Hwy 90, LLC, et al." on Justia Law
Perez v. Turner
In 2010, Houston voters approved “Proposition One,” allowing the city to create a “Pay-As-You-Go” Dedicated Drainage and Street Renewal (DDSR) Fund. Perez and others filed an election contest while the city enacted the Drainage Fee Ordinance (DFO), creating a new public utility and requiring Houston to establish drainage fees “against all real property in the city subject to such charges” and “provide drainage for all real property in the city on payment of drainage charges unless the property is exempt.” The DFO based the drainage fees on the benefited property’s type and square footage. Failure to pay drainage fees carried various penalties.In 2015, the Supreme Court held that Proposition One’s ballot language was misleading, rendering the Amendment invalid. Perez then challenged Houston’s assessment, collection, and expenditure of the drainage fee. In 2018, Houston passed a new charter amendment curing many of the defects Perez alleged in the drainage fee ordinance. Perez was left with ongoing claims for reimbursement of the drainage fees she paid before 2018 and for an injunction against the future expenditure of fees collected before 2018. The Texas Supreme Court affirmed the dismissal of those claims but remanded to allow Perez to replead in light of intervening events. Perez’s claims required her to articulate a viable theory of the DFO’s illegality to overcome Houston’s governmental immunity; her only theory failed as a matter of law. View "Perez v. Turner" on Justia Law
Dyer v. Texas Commission on Environmental Quality
TexCom sought to develop a commercial-waste-disposal facility on a 27-acre site in Montgomery County, near Conroe, that had one existing nonoperative injection well. TexCom sought to operate the existing well and construct up to three additional wells. Class I underground injection-control wells manage industrial waste by injecting it thousands of feet underground but can potentially harm drinking water and petroleum, so these injection wells undergo an extensive permitting process with the Texas Commission on Environmental Quality (TCEQ). A permit application must be accompanied by a letter from the Railroad Commission (RRC) concluding that the proposed wells “will not endanger or injure any known oil or gas reservoir.” RRC issued such a letter for TexCom but rescinded it after six years of administrative hearings, around the same time TCEQ issued its final order granting the permit application.The Texas Supreme Court affirmed TCEQ’s order granting the permit application as supported by substantial evidence; a migration finding, combined with the injection zone’s geological suitability, is sufficient to support TCEQ’s ultimate finding that the wells would be protective of water. The rescission did not deprive TCEQ of jurisdiction, and, on these facts, TCEQ did not violate the Texas Administrative Procedure Act by declining to reopen the administrative record for further proceedings. View "Dyer v. Texas Commission on Environmental Quality" on Justia Law
Dunham v. Lake County Commission
The Supreme Court reversed the judgment of the circuit court dismissing Petitioner's petition for a writ of certiorari challenging the Lake County Board's decision to grant a variance to Hodne Homes, LLC to build a facility to store and display boats, holding that the circuit court erred.In Dunham I, the Supreme Court reversed the circuit court's denial of Petitioner's challenge to the variance. On remand, the circuit court addressed a newly-raised issue about Petitioner's standing and then dismissed the petition because of a lack of standing. The Supreme Court reversed, holding that Petitioner was an "aggrieved" party with standing to challenge the variance under S.D. Codified Laws 11-2. View "Dunham v. Lake County Commission" on Justia Law
3G AG LLC v. IDWR
This appeal centered around the Idaho Department of Water Resources' (“IDWR”) denial of Application 83160, brought by Jeffrey and Chana Duffin (“Duffin”), to transfer the licensed ground water right 35-7667 to a different parcel of land. During the appeal of this case, 3G AG LLC (“the LLC”) “purchased from Duffin the property where water right 35-7667 - the water right subject to Transfer No. 8316 which is the subject of this appeal - is located.” As a result of the transfer of ownership, the LLC sought to substitute itself for Duffin. Because there was no objection to the substitution, it was allowed. IDWR denied the transfer because, among other reasons, approving it would cause an “enlargement” in the use of water as proscribed by Idaho Code section 42-222(1). On judicial review, the district court agreed with the denial and affirmed. Finding no error in the district court's judgment, the Idaho Supreme Court affirmed the decision of the district court. View "3G AG LLC v. IDWR" on Justia Law