Justia Government & Administrative Law Opinion Summaries

Articles Posted in Zoning, Planning & Land Use
by
Appellant North West Neighborhood Association challenged a district court’s decision upholding Boise City Council’s approval of three interrelated land use applications. The Idaho Supreme Court agreed with Appellant that Boise City Council failed to provide a reasoned statement explaining its approval of the applications as required by section 67-6535(2) of the Local Land Use Planning Act. The Court remanded this matter to the district court with instructions to set aside Boise City Council’s actions and remand to the Council for the adoption of a reasoned statement. View "NW Neighborhood Assoc v. City of Boise" on Justia Law

by
In this zoning dispute involving the interplay between the public's interest in the future of a private airport in Prince George's County and the financial interests of its owner, the Supreme Court held that the amended zoning ordinance allowing the airport to develop higher-density housing did not violate Maryland's uniformity requirement, Md. Code Ann., Land Use 22-201(b)(2)(i).When the airport's owners began experiencing financial difficulties they sought to redevelop the site, which had been limited by the zoning ordnance to low-density, single-family detached housing, for non-airport use. The County Council amended the zoning ordinance to allow for higher-density housing to incentivize the airport's redevelopment. Plaintiffs brought suit. The circuit court concluded that the ordinance did not violate uniformity, but the appellate court reversed, finding that the ordinance violated uniformity because it was tailored so narrowly as to afford favorable development opportunities to only the airport property. The Supreme Court reversed, holding that the ordinance was adopted to further a valid public purpose and did not discriminate against similarly situated properties, thus surviving the uniformity challenge. View "Prince George's County v. Concerned Citizens" on Justia Law

by
Plaintiffs Bradley Weiss and Cathleen Shea appealed a superior court order granting defendant Town of Sunapee's (Town) motion to dismiss. The trial court determined that, because plaintiffs failed to request a second rehearing from the Town’s Zoning Board of Adjustment (ZBA), the court did not have subject matter jurisdiction over their appeal. The New Hampshire Supreme Court reversed and remanded: pursuant to RSA 677:3, plaintiffs perfected their appeal to the superior court from the ZBA’s April 1 denial by timely moving for rehearing. View "Weiss, et al. v. Town of Sunapee" on Justia Law

by
The Supreme Judicial Court vacated the judgment of the superior court denying Appellants' Me. R. Civ,. P. 80B petition for review of government action and affirming the decision of the Portland Planning Board to approve 37 Montreal LLC's application to construct a multi-unit residential building, holding that the Planning Board did not err in approving the application.On appeal, Appellants argued that the proposed development failed to meet the City of Portland's Code of Ordinance's height, setback, and design-review requirements, and therefore, the Planning Board erred in approving the application. The Supreme Judicial Court vacated the judgment below and remanded the matter to the Planning Board for findings of fact, holding that judicial review was impossible because the Planning Board's decision did not contain any of the required findings. View "Murray v. City of Portland" on Justia Law

by
In 2015, the Department of Transportation (“PennDOT”) began constructing a diamond interchange and installing a drainage system on property abutting Interstate 70 (“I-70”) in Washington County, Pennsylvania. The property’s owner, Appellant Donald Bindas, petitioned for the appointment of a board of viewers, seeking compensation for this encumbrance upon his land. PennDOT asserted that its predecessor, the Department of Highways (“DOH”), had secured a highway easement for the land in question in 1958. Both the trial court and the Commonwealth Court agreed, dismissing Bindas’ suit. Upon its review of the statutory authority that PennDOT invoked, as well as the record, the Pennsylvania Supreme Court found that DOH’s failure to comply with the requirements of 36 P.S. § 670-210 rendered that easement invalid. Accordingly, the Court vacated the Commonwealth Court’s order, and remanded with the instruction that PennDOT’s preliminary objections be overruled. View "Bindas. v. PennDOT" on Justia Law

by
Appellant Tanner Altizer suffered serious injuries when he ran into a suspended cable fence while riding his off-road motorcycle on an unpaved area in an unoccupied area of the desert. The owner of the property, respondent Coachella Valley Conservation Commission (the Commission), placed the cable fence around its property to stop illegal dumping and off-road vehicles in order to protect the sensitive habitat. Altizer sued the Commission, alleging that the cable fence created a dangerous condition on public property. The trial court granted summary judgment for the Commission, and Altizer appealed. After review, the Court of Appeal concluded the Commission was entitled to hazardous recreational activity immunity under Government Code section 831.71 and affirmed. View "Altizer v. Coachella Valley Conservation Com." on Justia Law

by
The County of Santa Barbara (County) appealed from the entry of a preliminary injunction prohibiting its Road Commissioner from removing unpermitted encroachments placed in the public right of way along a portion of East Mountain Drive in Montecito. The County filed a cross-complaint alleging causes of action for public nuisance and trespass against respondents. The trial court issued a preemptory writ that suspends all efforts by County to enforce the right-of-way encroachments.   The Second Appellate District concluded that the trial court erred because Respondents are not correct on the merits of their CEQA claim and will not be irreparably harmed by the removal of encroachments installed without permits in the public right of way of an existing road. The County Road Commissioner is authorized by statute and local ordinance to remove any encroachment on a public right of way. The court explained that Respondents will suffer no irreparable harm because a party suffers no grave or irreparable harm by being prohibited from violating the law. View "Anderson v. County of Santa Barbara" on Justia Law

by
The Day family and Trust B of the Donald M. Day and Marjorie D. Day Family Trust appealed a district court’s decision to grant the Idaho Transportation Department’s (“ITD”) motion for involuntary dismissal. ITD cross-appealed, arguing that the district court erred in denying its request for attorney fees under Idaho Code section 12-120(3). In 1961, the Days learned that access to their property via public highways would be affected when the state highway converted to a controlled-access federal interstate highway, then known as Interstate 80. The Days entered into a preliminary agreement with the Idaho Department of Highways (“IDH,” predecessor to ITD) that allowed IDH to take possession of approximately nine acres of the Day Property for construction of the interstate. In 1967, the Days entered into a right-of-way contract with IDH in furtherance of the 1961 Agreement. The 1967 Contract included an agreement for IDH to provide access to a future frontage road from I-80 to the Day Property. In the 1990s, the State began construction on the Isaacs Canyon Interchange near the Day Property. The Interchange Project eliminated a portion of the original 50-foot right of way that provided access to the Day Property under the 1967 Contract. Because of this, ITD provided replacement access easements to the Day Property. These replacement access easements were located southwest of the Interstate. The Days informed ITD the family was dissatisfied with the replacement easements and did not think they afforded the Days equivalent access to what they had prior to the construction of the Interchange. The Days sold the property to Edmonds Groves Land Holdings Inc. (“Groves”) in 2005, with the purchase price secured by a mortgage held by the Day Family. Groves later defaulted in its mortgage agreement with the Days during the recession in December of 2008. As a result, ownership of the Day Property reverted to the Day Family by way of deed in lieu of foreclosure. After the Days reacquired the property, they had difficulty obtaining title insurance because of concerns that “the access easement was owned by ITD and [the Days] did not have any statement that the easement was for the benefit of the Days.” They sued alleging inverse condemnation, and breach of contract. Finding no reversible error in the district court's dismissal, the Idaho Supreme Court affirmed. View "Day v. Idaho Transportation Department" on Justia Law

by
The Supreme Court upheld the final determination of the Maryland Department of the Environment to reissue with revisions a general discharge permit to Animal Feeding Operations (AFOs), holding that the Department's final determination was reasonable and complied with applicable water quality standards.The most recent iteration of the general discharge permit the Department issued to AFOs was finalized by the Department pursuant to certain statutory requirements requiring the Department to review and issue or reissue water pollution control permits once every five years. The circuit court vacated the permit and remanded the matter with instructions to incorporate certain water quality standards into the permit. The Supreme Court reversed the judgment of the circuit court, holding (1) the Department's AFO general discharge permit framework was reasonable and consistent with federal and state law; and (2) the Department's decision to evaluate each AFO individually and to require appropriately-tailored best-management practices to control the emissions where they presented a risk of discharge was reasonable and not an abuse of discretion. View "Dep't of Environment v. Assateague Coastal Trust" on Justia Law

by
In the first appeal arising from Plaintiff-respondent Margaret McCann’s dispute with the City of San Diego over the City’s environmental review process of a project to convert overhead utility wires to an underground system in several neighborhoods, she alleged the City violated the California Environmental Quality Act (CEQA) by failing to properly consider the environmental impact of two underground projects. The Court of Appeal concluded the City’s review process was incomplete as to one project (MND Project) because the City failed to analyze whether they were consistent with the City’s Climate Action Plan. The judgment was reversed and the case remanded for the trial court to issue a peremptory writ of mandate ordering the City of set aside three resolutions that approved the projects. After remand, the trial court also ordered it would retain jurisdiction over the matter until the City complied with the relevant provisions of the CEQA. The City rescinded the project approvals and asked the court to discharge the writ. McCann objected to the City’s return and argued the trial court should not discharge the writ because the City did not perform the relevant analysis or affirmatively indicate it abandoned the projects. The trial court sustained McCann’s objection and declined to discharge the writ. The City then appealed, arguing it fully complied with the courts’ mandates. After review, the Court of Appeal determined the City satisfied the writ, and therefore held the writ had to be discharged. View "McCann v. City of San Diego" on Justia Law